Showing 1261 to 1280 of 2747 projects. Download as CSV

Project Contractor Agency Type Budget Progress Started Target date
Improvement of Road, Barangay Payatas, Quezon City
Ongoing SDG 9SDG 11
R. Rose Construction Services Quezon City 1st DEO Roads ₱24,374,948 99% 2025-02-20 —
Improvement of Road, Barangay Mariana, Quezon City
Completed SDG 9SDG 11
YPR GEN. Contractor AND Construction Supply INC. Quezon City 2nd DEO Roads ₱48,998,099 100% 2024-02-23 —
Improvement of Road, Barangay Laging Handa, Quezon City
Completed SDG 9SDG 11
Great Pacific Builders AND GEN. Contractor INC. ([Revoked] 45914) Quezon City 2nd DEO Roads ₱48,998,664 100% 2024-02-28 —
Improvement of Road, Barangay Holy Spirit, Quezon City
Ongoing SDG 9SDG 11
Sherrah Construction Quezon City 1st DEO Roads ₱24,229,733 24% 2025-02-20 —
Improvement of Road, Barangay Commonwealth, Quezon City
Ongoing SDG 9SDG 11
CV East Construction Corporation Quezon City 1st DEO Roads ₱24,229,986 74% 2025-02-20 —
Improvement of Road, Barangay Batasan Hills, Quezon City
Ongoing SDG 9SDG 11
CV East Construction Corporation Quezon City 1st DEO Roads ₱24,377,404 22% 2025-02-20 —
Improvement of Road, Barangay Bagong Silangan, Quezon City
Ongoing SDG 9SDG 11
CV East Construction Corporation Quezon City 1st DEO Roads ₱24,319,828 25% 2025-02-20 —
Improvement of Road, Barangay Baesa, Quezon City
Completed SDG 9SDG 11
Rosand Builders Corporation (Formerly: Rosand Builders) Quezon City 1st DEO Roads ₱18,963,562 100% 2022-05-19 —
Improvement of Road, Banawe ST., Quezon City
Completed SDG 9SDG 11
Dimaguila Construction & Supply, INC. Quezon City 2nd DEO Roads ₱11,704,912 100% 2018-02-02 —
Improvement of Road at Barangay STA. Monica, Quezon City
Ongoing SDG 9SDG 11
LE Bron Construction Quezon City 1st DEO Roads ₱48,117,065 61% 2025-03-06 —
Improvement of Road at Barangay Novaliches Proper, Quezon City
Ongoing SDG 9SDG 11
Framecon Builders Quezon City 1st DEO Roads ₱48,117,717 0% 2025-03-03 —
Improvement of Road at Barangay Fairview, Quezon City
Ongoing SDG 9SDG 11
LE Bron Construction Quezon City 1st DEO Roads ₱94,762,794 30% 2025-03-03 —
Improvement of Road and Drainage in Sierra Madre ST. in Brgy. Kaligayahan, Quezon City
Ongoing SDG 9SDG 11
Steelman Builders Corporation Quezon City 1st DEO Roads ₱9,800,310 73% 2024-02-16 —
Improvement of Road and Drainage in SAN Ildefonso ST. in Brgy. Nagkaisang Nayon, Quezon City
Completed SDG 9SDG 11
10 Builders AND Development Corporation Quezon City 1st DEO Roads ₱9,897,913 100% 2024-02-16 —
Improvement of Road and Drainage in SAN Fernando ST. in Brgy. Nagkaisang Nayon, Quezon City
Completed SDG 9SDG 11
A.T. Dumlao Construction, INC. Formerlyandoni T. D Quezon City 1st DEO Roads ₱9,899,663 100% 2024-02-16 —
Improvement of Road and Drainage in Morena Blanco ST. in Brgy. STA. Monica, Quezon City
Completed SDG 9SDG 11
Steelman Builders Corporation Quezon City 1st DEO Roads ₱9,897,540 100% 2024-02-16 —
Improvement of Road and Drainage in Carreon Aguirre in Brgy. SAN Bartolome, Quezon City
Completed SDG 9SDG 11
Framecon Builders Quezon City 1st DEO Roads ₱19,601,951 100% 2024-02-16 —
Improvement of Road and Drainage, Barangay Nagkaisang Nayon Road, Quezon City
Completed SDG 9SDG 11
E.L. Anolin Construction Quezon City 1st DEO Roads ₱48,955,468 100% 2024-02-27 —
Improvement of Road and Drainage at Sunflower ST., Brgy. Payatas, Quezon City
Completed SDG 9SDG 11
Diadema Construction AND Enterprises INC. (Formerly: Diadema Enterprises) Quezon City 1st DEO Roads ₱4,901,262 100% 2023-04-26 —
Improvement of Road along Barangay Pasong Putik, Quezon City
Ongoing SDG 9SDG 11
LE Bron Construction Quezon City 1st DEO Roads ₱94,569,899 29% 2025-04-04 —