Showing 1241 to 1260 of 2747 projects. Download as CSV

Project Contractor Agency Type Budget Progress Started Target date
Improvement of Roads, at Barangay DOÑA Imelda, Quezon City
Completed SDG 9SDG 11
Royalink Builders, INC. Quezon City 2nd DEO Roads ₱14,691,142 100% 2020-11-27 —
Improvement of Roads, at Barangay Botocan, Quezon City
Completed SDG 9SDG 11
Dela Rosa Construction & DEV'T. Corp. (Formerly: Z Quezon City 2nd DEO Roads ₱7,913,472 100% 2020-11-27 —
Improvement of Roads and Drainage at Brgy. SAN Martin DE Porres, Quezon City
Completed SDG 9SDG 11
Royalink Builders, INC. Quezon City 2nd DEO Roads ₱11,112,337 100% 2020-11-27 —
Improvement of Road, Samar ST., Quezon City
Completed SDG 9SDG 11
R.A. Pahati Const. & Supply, INC. Quezon City 2nd DEO Roads ₱57,872,276 100% 2018-02-19 —
Improvement of Road, Roces AVE., Quezon City
Completed SDG 9SDG 11
Ayana Construction AND Trading Quezon City 2nd DEO Roads ₱4,653,323 100% 2018-02-02 —
Improvement of Road, Panay Avenue, Quezon City
Completed SDG 9SDG 11
MRB11 Construction Corporation (Formerly:MRB Cons Quezon City 2nd DEO Roads ₱65,089,638 100% 2018-03-16 —
Improvement of Road, Panay Avenue, Phase III, Brgy. Paligsahan, Quezon City
Completed SDG 9SDG 11
MRB11 Construction Corporation (Formerly:MRB Cons Quezon City 2nd DEO Roads ₱18,598,401 100% 2019-09-06 —
Improvement of Road Network Within University of the Philippines Diliman Campus, Quezon City
Completed SDG 9SDG 11
MRB11 Construction Corporation (Formerly:MRB Cons Quezon City 2nd DEO Roads ₱48,407,819 100% 2019-07-26 —
Improvement of Road, Mapagmahal ST., Quezon City
Completed SDG 9SDG 11
Czerj Construction & Trading Quezon City 2nd DEO Roads ₱14,426,416 100% 2018-02-02 —
Improvement of Road, Malakas ST., Quezon City
Completed SDG 9SDG 11
MOM Enterprises Quezon City 2nd DEO Roads ₱27,694,179 100% 2018-02-02 —
Improvement of Road Including Drainage System, Banahaw ST., Group 2, Area B, Barangay Payatas, Quezon City
Completed SDG 9SDG 11
Rostel Construction & Supply Quezon City 1st DEO Roads ₱12,004,324 100% 2024-02-23 —
Improvement of Road, DOÑA Nicasia, Barangay Commonwealth, Quezon City
Completed SDG 9SDG 11
IM Construction Corporation Quezon City 1st DEO Roads ₱14,552,852 100% 2024-03-13 —
Improvement of Road, DAU ST. Feria Compound, Barangay OLD Balara, Quezon City
Completed SDG 9SDG 11
Metrics Construction & Trading Quezon City 2nd DEO Roads ₱947,811 100% 2018-03-16 —
Improvement of Road, Brgy. Payatas, Quezon City
Ongoing SDG 9SDG 11
Legacy Construction Corporation (Formerly: Legacy Construction) / EMQ Design & Construction Quezon City 1st DEO Roads ₱37,279,910 94% 2024-02-27 —
Improvement of Road, Brgy. Holy Spirit, Quezon City
Completed SDG 9SDG 11
A.J. Lava Builders Corp. (Formerly: A.J. Lava Buil Quezon City 1st DEO Roads ₱24,499,854 100% 2024-02-16 —
Improvement of Road, Brgy. Commonwealth, Quezon City
Completed SDG 9SDG 11
CV East Construction Corporation Quezon City 1st DEO Roads ₱20,371,830 100% 2024-03-13 —
Improvement of Road, Brgy. Bagong Silangan, Quezon City
Completed SDG 9SDG 11
CV East Construction Corporation Quezon City 1st DEO Roads ₱24,254,866 100% 2024-02-16 —
Improvement of Road, Barangay South Triangle, Quezon City
Completed SDG 9SDG 11
Great Pacific Builders AND GEN. Contractor INC. ([Revoked] 45914) Quezon City 2nd DEO Roads ₱48,999,200 100% 2024-02-15 —
Improvement of Road, Barangay SAN Roque, Package 2, Quezon City
Ongoing SDG 9SDG 11
Alrie Construction Services Quezon City 2nd DEO Roads ₱94,465,924 51% 2025-04-11 —
Improvement of Road, Barangay Sacred Heart, Quezon City
Completed SDG 9SDG 11
YPR GEN. Contractor AND Construction Supply INC. Quezon City 2nd DEO Roads ₱48,930,382 100% 2024-02-28 —