Preventive Maintenance - Primary Roads: Aurora Blvd - K0013 + 290 - K0011 + 599, K0010 + 213 - K0010 +364, Quezon City
Ongoing
SDG 9SDG 11
|
Alrie Construction Services |
Quezon City 2nd DEO |
Roads |
₱75,577,493 |
92% |
2025-04-11 |
— |
|
Preventive Maintenance - Primary Roads: Aurora Blvd - K0010 + (-408) - K0011 + 000, K0012 + 453 - K0013 + 079, Quezon City
Ongoing
SDG 9SDG 11
|
Alrie Construction Services |
Quezon City 2nd DEO |
Roads |
₱75,580,070 |
96% |
2025-06-10 |
— |
|
Preventive Maintenance of Road: Conrete Reblocking-C-5 Road (S05616LZ) K0015+-1060-K0015+184, Quezon City
Completed
SDG 9SDG 11
|
NEW Arcond Builders Incorporated (Formerly Arcond |
Quezon City 2nd DEO |
Roads |
₱16,381,510 |
100% |
2019-07-12 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Regalado AVE (North) - K0024 + (-108) - K0024 + 000, K0024 + (-758) - K0024 + (-108), Quezon City
Completed
SDG 9SDG 11
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 1st DEO |
Roads |
₱10,620,687 |
100% |
2024-02-23 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Quirino HI-WAY - K0014 + 294 - K0018 + 000, K0019 + 000 - K0019 + 740, Quezon City
Completed
SDG 9SDG 11
|
LE Bron Construction |
Quezon City 1st DEO |
Roads |
₱69,734,396 |
100% |
2023-02-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Payatas RD - K0026 + 500 - K0027 + 559, Quezon City
Completed
SDG 9SDG 11
|
Legacy Construction Corporation (Formerly: Legacy Construction) |
Quezon City 1st DEO |
Roads |
₱14,552,535 |
100% |
2024-02-23 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Payatas RD - K0024 + 700 - K0025 + 230, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱18,299,556 |
100% |
2024-02-23 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Payatas RD - K0023+780 - K0024+700, Quezon City
Completed
SDG 9SDG 11
|
Miles Trading AND Construction |
Quezon City 1st DEO |
Roads |
₱51,198,592 |
100% |
2024-03-18 |
— |
|
Preventive Maintenance of Road : Concrete Reblocking-Ortigas-Granada RD-K0010+(-205)-K0010+(-016), Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 2nd DEO |
Roads |
₱3,028,350 |
100% |
2020-10-09 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Mindanao AVE., K0014+(-589) - K0014+000, K0014+(-689) - K0014+(-589), K0014+000 - K0014+23, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱5,353,928 |
100% |
2021-03-01 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - G. Araneta AVE. - K0011 + (-891) - K0011 + 000, Quezon City
Completed
SDG 9SDG 11
|
Triches Construction & Trading |
Quezon City 1st DEO |
Roads |
₱13,948,045 |
100% |
2023-02-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos Avenue (Edsa) - K0013+000 - K0013+617, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱15,319,206 |
100% |
2024-06-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE. (Edsa) (S05142LZ) - K0020 + (-080) - K0020 + 000, K0020 + (-778) - K0020 + (-080), K0020 + 000 - K0020 + 493, Quezon City
Completed
SDG 9SDG 11
|
Rend Enterprises & General Contractor |
Quezon City 2nd DEO |
Roads |
₱18,796,104 |
100% |
2022-02-11 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE. (Edsa) (S05132LZ) - K0016 + (-239) - K0016 + (-006), K0016 + (-431) - K0016 + (-239), K0016 + (-536) - K0016 + (-431), K0016 + 1152 - K0017 + 252, K0016 .... Quezon City
Completed
SDG 9SDG 11
|
Elite General Contractor AND Development Corp. |
Quezon City 2nd DEO |
Roads |
₱28,223,395 |
100% |
2022-02-11 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE (Edsa) - K0015 + (-432) - K0015 + (-047), Quezon City
Completed
SDG 9SDG 11
|
IM Construction Corporation |
Quezon City 1st DEO |
Roads |
₱9,649,087 |
100% |
2024-06-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE (Edsa) - K0014 + 200 - K0013 + 000, Quezon City
Completed
SDG 9SDG 11
|
IM Construction Corporation |
Quezon City 1st DEO |
Roads |
₱18,734,905 |
100% |
2024-06-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE (Edsa) - K0014 + 082 - K0014 + 467, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱9,649,140 |
100% |
2024-06-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE., (Edsa), K0013+969 - K0014+247, Quezon City
Completed
SDG 9SDG 11
|
E.L. Anolin Construction |
Quezon City 1st DEO |
Roads |
₱4,792,406 |
100% |
2021-03-01 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE (Edsa) - K0013 + 632 - K0014 + 000, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱10,645,210 |
100% |
2024-06-13 |
— |
|
Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE. (Edsa) - K0012 + 786 - K0013 + 632, Quezon City
Completed
SDG 9SDG 11
|
E.L. Anolin Construction |
Quezon City 1st DEO |
Roads |
₱21,033,984 |
100% |
2023-02-13 |
— |