Proposed Installation of Pumps and Its Facilities/Appurlinances at Malacañang Compound
Completed
Approximate location
SDG 9SDG 11
|
MSB Vitug Construction |
North Manila District Engineering Office |
Roads |
₱29,228,000 |
100% |
2013-03-26 |
2014-05-21 |
|
Proposed Excavation/Desilting of San Juan River (Sta 3+025-Sta 3+495) Dredging/Desilting
Completed
Approximate location
SDG 9SDG 11
|
Werr Corporation International |
Metro Manila 1st District Engineering Office |
Roads |
₱36,480,000 |
100% |
2014-10-23 |
2015-02-19 |
|
Proposed Excavation/Desilting of San Juan River (Sta 2+475-Sta 3+025) Dredging/Desilting
Completed
Approximate location
SDG 9SDG 11
|
AKN Construction Corporation |
Metro Manila 1st District Engineering Office |
Roads |
₱40,305,000 |
100% |
2014-07-08 |
2014-11-04 |
|
Proposed Excavation/Desilting of Salapan Creek (Sta. 0+000 to Sta. 0+900) Dredging/Desilting
Completed
Approximate location
SDG 9SDG 11
|
Werr Corporation International |
Metro Manila 1st District Engineering Office |
Roads |
₱24,937,000 |
100% |
2014-07-01 |
2014-09-28 |
|
Proposed Dredging/Deepening of Marikina River Sta. 5+200-Sta. 6+100 Upstream of Rosario Bridge Pasig City
Completed
Approximate location
SDG 9SDG 11
|
MSB Vitug Construction |
Metro Manila 1st District Engineering Office |
Bridges |
₱47,000,000 |
100% |
2013-05-16 |
2013-09-12 |
|
Proposed Drainage Improvement Works around Bahay Pangarap in Malacañang Park
Completed
Approximate location
SDG 11SDG 13
|
A.L. Dare Construction |
North Manila District Engineering Office |
Flood control & drainage |
₱16,686,000 |
100% |
2013-03-27 |
2014-05-20 |
|
Proposed Construction of the University of the Philippines Diliman Swimming Pool and Stadium, Quezon City
Ongoing
SDG 9
|
G.F. Fabian Construction |
Quezon City 2nd DEO |
Buildings & facilities |
₱84,462,811 |
25% |
2022-07-29 |
— |
|
Proposed Construction of Revetment with Pile Cap along Pasig River at the Malacañang Palace Heroes Hall
Completed
Approximate location
SDG 11SDG 13
|
MSB Vitug Construction |
North Manila District Engineering Office |
Flood control & drainage |
₱47,923,000 |
100% |
2013-03-27 |
2014-06-21 |
|
Proposed Construction of Revetment Wall at the Left Side of Santibañez Pumping Station
Completed
Approximate location
SDG 11SDG 13
|
Mjbz Builders AND Trading |
North Manila District Engineering Office |
Flood control & drainage |
₱4,634,000 |
100% |
2013-07-01 |
2014-05-17 |
|
Proposed Construction of Property and Supply Building (Three (3) Storey) Quezon City General Hospital, Q.C.
Completed
SDG 9
|
Framecon Builders |
Quezon City 1st DEO |
Buildings & facilities |
₱18,611,284 |
100% |
2017-04-25 |
— |
|
Preventive Maintenance - Visayas AVE., K0014+000 - K0013+000, Quezon City
Completed
SDG 9SDG 11
|
Mdridr Const. & DEV'T. Corp. (Formerly: I.D.R. Construction) |
Quezon City 1st DEO |
Roads |
₱9,341,194 |
100% |
2020-12-02 |
— |
|
Preventive Maintenance - Visayas AVE., - K0012+000 - K0013+166, Quezon City
Completed
SDG 9SDG 11
|
Chrizmarie Builders AND Construction Supply |
Quezon City 1st DEO |
Roads |
₱12,946,929 |
100% |
2020-12-02 |
— |
|
Preventive Maintenance - Tertiary Roads - Visayas AVE., - K0012+(-079) - K0014+328, Quezon City
Completed
SDG 9SDG 11
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱96,498,455 |
100% |
2022-05-19 |
— |
|
Preventive Maintenance - Tertiary Roads: Tomas Morato - K0009 + (-091) - K0009 + 1593, Quezon City
Completed
SDG 9SDG 11
|
Jjpr Construction Services |
Quezon City 2nd DEO |
Roads |
₱66,189,479 |
100% |
2025-04-11 |
— |
|
Preventive Maintenance - Tertiary Roads - Times ST - K0010 + (-020) - K0011 + 260, Quezon City
Ongoing
SDG 9SDG 11
|
Golden J'S Construction Services |
Quezon City 1st DEO |
Roads |
₱48,019,400 |
0% |
2025-04-04 |
— |
|
Preventive Maintenance - Tertiary Roads - Susano RD - K0019 + 450 - K0019 + 845, Quezon City
Ongoing
SDG 9SDG 11
|
AVE-Mira Construction AND Trading |
Quezon City 1st DEO |
Roads |
₱19,246,619 |
83% |
2025-03-04 |
— |
|
Preventive Maintenance - Tertiary Roads: SCT. Lozano - K0009 + (-877) - K0009 + 408, Quezon City
Ongoing
SDG 9SDG 11
|
WAY Maker General Contractor OPC ([Revoked] 52351) |
Quezon City 2nd DEO |
Roads |
₱18,199,816 |
0% |
2025-03-25 |
— |
|
Preventive Maintenance - Tertiary Roads - SCT. Alcaraz (S05342LZ) - K0007+(-860) - K0007+649, Quezon City
Ongoing
SDG 9SDG 11
|
L.R. Tiqui Builders, INC. / 729 Construction, INC. (Formerly 722 Construction, INC.) |
Quezon City 1st DEO |
Roads |
₱96,499,246 |
89% |
2025-02-20 |
— |
|
Preventive Maintenance - Tertiary Roads - Regalado AVE (North) - K0024 + (-758) - K0025 + 1012, Quezon City
Ongoing
SDG 9SDG 11
|
LE Bron Construction |
Quezon City 1st DEO |
Roads |
₱94,550,433 |
56% |
2025-04-07 |
— |
|
Preventive Maintenance - Tertiary Roads - Regalado AVE (North) - K0024 + (-095) - K0025 + 000, Quezon City
Completed
SDG 9SDG 11
|
CG General Construction & Development Corporation |
Quezon City 1st DEO |
Roads |
₱47,355,424 |
100% |
2025-03-03 |
— |