|
Widenning of Bridge - Culiat BR. 3 (SB) (BO2356LZ) along Visayas AVE., Quezon City
Completed
SDG 9SDG 11
|
E.L. Anolin Construction (35406) |
Quezon City 1st DEO |
Bridges |
₱9,506,754 |
100% |
2021-07-05 |
— |
|
Widening of Road and Drainage Improvement of Eugenio Lopez Drive, Quezon City
Completed
SDG 9SDG 11
|
Nueda Builders Construction & Supply INC. (39776) |
Quezon City 2nd DEO |
Roads |
₱9,267,696 |
100% |
2018-02-02 |
— |
|
Widening of Road and Drainage Improvement of 11TH Jamboree ST., Quezon City
Completed
SDG 9SDG 11
|
Nueda Builders Construction & Supply INC. (39776) |
Quezon City 2nd DEO |
Roads |
₱14,633,280 |
100% |
2018-02-02 |
— |
|
Widening of General Luis Street including ROW Valenzuela Caloocan and Quezon City Widening - Gravel
Ongoing
Approximate location
SDG 9SDG 11
|
— |
Regional Office |
Roads |
₱5,000,000 |
— |
— |
— |
|
Widening of C-5 Kalayaan and C-5 Bagong Ilog Fly-over Pasig City Construction OF NEW Bridge
Ongoing
Approximate location
SDG 9SDG 11
|
— |
Metro Manila 1st District Engineering Office |
Bridges |
₱500,000,000 |
— |
— |
— |
|
Widening of Bridge - Pasong Tamo BR. 2 (SB) (BO2355LZ) along Visayas AVE., Quezon City
Completed
SDG 9SDG 11
|
E.L. Anolin Construction (35406) |
Quezon City 1st DEO |
Bridges |
₱14,259,000 |
100% |
2021-07-05 |
— |
|
Widening of Bridge - Pasong Tamo BR. 2 (NB) (BO2357LZ) along Visayas AVE., Quezon City
Completed
SDG 9SDG 11
|
R.A. Pahati Const. & Supply, INC. (35843) |
Quezon City 1st DEO |
Bridges |
₱14,259,000 |
100% |
2021-06-07 |
— |
|
Widening of Bridge - Culiat BR. 3 (NB) (BO2358LZ) along Visaya AVE., Quezon City
Completed
SDG 9SDG 11
|
R.A. Pahati Const. & Supply, INC. (35843) |
Quezon City 1st DEO |
Bridges |
₱9,506,754 |
100% |
2021-06-07 |
— |
|
Widening of Bonny Serrano Avenue, Quezon City
Completed
SDG 9SDG 11
|
M.V. Caldo Construction AND Supply Corporation (Formerly: M.V. Caldo Engineering Construction AND S) (16938) / C.T. Leoncio Construction & Trading (17371) |
Quezon City 2nd DEO |
Roads |
₱76,726,870 |
100% |
2020-02-17 |
— |
|
Valenzuela-Obando-Meycauayan Flood Control Project - Construction of Coastal Dike Phase II Navotas City Sta.1+523 to Sta. 2+295 Construction
Ongoing
Past target date
Approximate location
SDG 11SDG 13
|
E.M. Cuerpo, INC. |
Malabon-Navotas District Engineering Office |
Flood control & drainage |
₱265,219,000 |
20% |
2015-12-29 |
2016-11-20 |
|
Upgrading of Roads Including Drainage at Mines and Other Streets of Barangay Vasra, Quezon City
Completed
SDG 9SDG 11
|
Oscord Builders Corporation (44137) |
Quezon City 1st DEO |
Roads |
₱28,135,626 |
100% |
2023-03-15 |
— |
|
UI-2 Lipa-Alaminos Road Section K0000+000.00 to K0079+000.00 Lipa-Alaminos Road Improvement project Batangas & Laguna Region IV-A Paved (Concrete) TO Paved (Concrete)
Completed
SDG 9SDG 11
|
R.D. Policarpio & Company INC. |
Inter-District |
Roads |
₱205,115,000 |
100% |
2014-01-09 |
2015-04-03 |
|
Traffic Signalization of Intersections of MM: 1) Digitalized Hardware & Software System & Upgrading of 111 On-Line Intersections Repl. of Comptroller Road Safety Devices (Guardrails Pavement Markings Interesection Impvt.)
Ongoing
Approximate location
SDG 9SDG 11
|
— |
Regional Office |
Roads |
₱300,000,000 |
— |
— |
— |
|
Supply and inst. of LED Traffic Signal Lantern Assembly incl. removal of Old Incandescent Type Signal Lanterns at 38 Signalized Intersections Phase 1 Road Safety Devices (Guardrails Pavement Markings Interesection Impvt.)
Completed
Approximate location
SDG 9SDG 11
|
Traffic Supplies & Construction Corp. |
Regional Office |
Roads |
₱38,116,000 |
100% |
2013-03-20 |
2013-12-20 |
|
Supply and Installation of Surgical Lights @ Operating Room Complex PGH Others
Completed
Approximate location
SDG 9SDG 11
|
By Administration |
South Manila District Engineering Office |
Roads |
₱32,000,000 |
100% |
2012-06-13 |
2013-01-08 |
|
Supply and Installation of Air conditioning (Variable refrigerant flow) system @ Operating Room Complex PGH Others
Completed
Approximate location
SDG 9SDG 11
|
By Administration |
South Manila District Engineering Office |
Roads |
₱18,000,000 |
100% |
2012-07-05 |
2013-01-30 |
|
Structural Retrofitting of the Department of Environment and Natural Resources (Denr) - Central Office Main Building, Visayas AVE., Diliman, Quezon City
Ongoing
SDG 9
|
IM Construction Corporation (20074) |
Quezon City 1st DEO |
Buildings & facilities |
₱66,052,316 |
41% |
2023-04-26 |
— |
|
Structural Improvement of Public Buildings and Construction of Evacuation Center, National Capital Region Ramon Magsaysay High School, H.E. Building, Quezon City
Completed
SDG 4
|
4 Doublers Trading & Contractor INC. (Formerly: 4 Doublers Trading AND Contractor) (35452) |
Quezon City 2nd DEO |
Buildings & facilities |
₱11,024,512 |
100% |
2020-01-10 |
— |
|
Structural Improvement of Public Buildings and Construction of Evacuation Center, National Capital Region: Libis Elementary School, H.E. Building, B. Serrano, Brgy. Libis, Quezon City
Completed
SDG 4
|
Alphatec Chemical Corporation (39938) |
Quezon City 2nd DEO |
Buildings & facilities |
₱3,797,618 |
100% |
2019-01-14 |
— |
|
Structural Improvement of Public Buildings and Construction of Evacuation Center, National Capital Region, Fort Aguinalo Elementary School Canteen, RD. 3 Corner D. 6, Camp General Emilio Aguinaldo, Quezon City
Completed
SDG 4
|
Alphatec Chemical Corporation (39938) |
Quezon City 2nd DEO |
Buildings & facilities |
₱1,944,777 |
100% |
2019-01-14 |
— |