Listahan ng proyekto

Paliitin ang mga proyekto ng gobyerno ayon sa nagtatayo, uri, katayuan, kailan nagsimula at magkano ang halaga. Ipinapakita ng mapa kung nasaan ang mga ito. Tingnan ang mga proyekto sa mapa

I-filter at ayusin
Higit pang mga filter

Burahin

Ipinapakita ang 1501 hanggang 1520 sa 2747 proyekto. I-download bilang CSV

Proyekto Kontratista Ahensya Uri Badyet Progreso Nagsimula Target na petsa
Construction/ Rehabilitation of Kagawad Road, Brgy. Batasan Hills, Quezon City
Natapos SDG 9SDG 11
Wawao Builders Quezon City 1st DEO Mga Kalsada ₱14,181,750 100% 2020-11-24 —
Construction/ Rehabilitation of Isidora Welfare Complex, Brgy. Holy Spirit, Quezon City
Natapos SDG 9
729 Construction, INC. (Formerly 722 Construction, INC.) Quezon City 1st DEO Mga Gusali at Pasilidad ₱14,181,750 100% 2020-11-24 —
Construction/ Rehabilitation of Heron ST., Brgy. Bagong Silangan, Quezon City
Natapos SDG 9SDG 11
Wawao Builders Quezon City 1st DEO Mga Kalsada ₱4,752,000 100% 2020-08-26 —
Construction / Rehabilitation of Health Center at Brgy. Culiat, Quezon City
Natapos SDG 9
C.L. Morales Construction AND Trading Quezon City 1st DEO Mga Gusali at Pasilidad ₱9,599,047 100% 2023-04-05 —
Construction/Rehabilitation of Gravity Wall along Intermittent Section along Ilog Pugad River Sta. 0+600-Sta. 1+100 (both side) East Side of Manggah
Natapos Tinatayang lokasyon SDG 9SDG 11
Franzcor Trading & Construction Rizal 1st District Engineering Office Mga Kalsada ₱9,324,000 100% 2012-11-27 2013-02-24
Construction/ Rehabilitation of Grants ST., Barangay Sangandaan, Quezon City
Natapos SDG 9SDG 11
Triches Construction & Trading Quezon City 1st DEO Mga Kalsada ₱14,259,000 100% 2020-11-24 —
Construction/ Rehabilitation of Freedom Park 1, Brgy. Batasan Hills, Quezon City
Natapos SDG 9
Datzlav Construction Quezon City 1st DEO Mga Gusali at Pasilidad ₱4,754,475 100% 2020-08-26 —
Construction / Rehabilitation of Flood Control Structures at Lumban Creek, Barangay Matandang Balara, Quezon City
Natapos SDG 11SDG 13
Perrc INC. (Formerly: P.E.R.R.C. Construction & Development Corporation) Quezon City 2nd DEO Kontrol sa Baha at Drainage ₱48,985,157 100% 2021-11-10 —
Construction/Rehabilitation of Flood Control Mitigation Facilities along Major River Basins and Principal River at Culiat Creek, Brgy. STO Cristo, Quezon City
Natapos SDG 11SDG 13
ST. Timothy Construction Corporation ([Revoked] 39196) Quezon City 1st DEO Kontrol sa Baha at Drainage ₱18,228,956 100% 2017-08-31 —
Construction / Rehabilitation of Everlasting Street, Brgy. Payatas, Quezon City
Natapos SDG 9SDG 11
C.E.M. Construction, INC. Quezon City 1st DEO Mga Kalsada ₱9,454,500 100% 2020-11-24 —
Construction/ Rehabilitation of Duyan-Duyan Creek (Inside Ateneo and Miriam Compound), Quezon City
Natapos SDG 11SDG 13
Tuchar Construction Corp. (Formerly:Tuchar Constru Quezon City 2nd DEO Kontrol sa Baha at Drainage ₱8,575,834 100% 2018-02-02 —
Construction/ Rehabilitation of Drainage along Miller ST., Veterans, Quezon City
Natapos SDG 11SDG 13
D.R. Robles Construction Quezon City 1st DEO Kontrol sa Baha at Drainage ₱9,696,120 100% 2020-11-24 —
Construction/ Rehabilitation of Drainage along Angelo ST., Brgy. N.S. Amoranto, Quezon City
Natapos SDG 11SDG 13
RED Matrix Builders AND Trading Quezon City 1st DEO Kontrol sa Baha at Drainage ₱3,422,160 100% 2020-08-26 —
Construction/ Rehabilitation of Dario Creek, Brgy. Tandang Sora, Quezon City
Natapos SDG 11SDG 13
C.E.M. Construction, INC. Quezon City 1st DEO Kontrol sa Baha at Drainage ₱28,809,000 100% 2021-04-28 —
Construction / Rehabilitation of College of LAW Building Including Site Development, UP Diliman, Quezon City
Natapos SDG 9
Mancol Construction Corporation Quezon City 2nd DEO Mga Gusali at Pasilidad ₱46,532,778 100% 2022-04-06 —
Construction/ Rehabilitation of Clemente Street, Lupang Pangako, Brgy. Payatas, Quezon City
Natapos SDG 9SDG 11
C.E.M. Construction, INC. Quezon City 1st DEO Mga Kalsada ₱18,909,000 100% 2020-11-24 —
Construction/Rehabilitation/Major Repair of Multi - Purpose Building, Brgy. Fairview, Quezon City
Natapos SDG 9
Aylan Construction & Trading Quezon City 1st DEO Mga Gusali at Pasilidad ₱2,880,590 100% 2017-08-31 —
Construction/ Rehabilitation/ Improvement of the Drug Treatment and Rehabiutation Center (Tahanan), Payatas, Quezon City
Natapos SDG 9
A. Dela Cruz Builders INC. Quezon City 1st DEO Mga Gusali at Pasilidad ₱11,309,760 100% 2020-11-24 —
Construction/ Rehabilitation/ Improvement of Multi-Purpose Building, Payatas, Quezon City
Natapos SDG 9
5-1 Construction Corporation Quezon City 1st DEO Mga Gusali at Pasilidad ₱18,057,360 100% 2022-03-22 —
Construction/ Rehabilitation/ Improvement of Multi-Purpose Building, Holy Spirit, Quezon City
Natapos SDG 9
P.J. Cruz Construction AND Trading Quezon City 1st DEO Mga Gusali at Pasilidad ₱12,355,217 100% 2022-03-22 —