Rehabilitation of Drainage System, Barangay Laging Handa, Quezon City
Natapos
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱29,698,540 |
100% |
2024-02-08 |
— |
|
Rehabilitation of Drainage System, Barangay Kamuning, Quezon City
Natapos
SDG 11SDG 13
|
Mancol Construction Corporation |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱29,697,365 |
100% |
2024-02-08 |
— |
|
Rehabilitation of Drainage System, Barangay Claro, Quezon City
Natapos
SDG 11SDG 13
|
Zali Construction, INC. |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱8,631,549 |
100% |
2023-02-15 |
— |
|
Rehabilitation of Drainage System, Barangay Blue Ridge B, Quezon City
Natapos
SDG 11SDG 13
|
4 Doublers Trading & Contractor INC. (Formerly: 4 Doublers Trading AND Contractor) |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱11,755,100 |
100% |
2023-05-31 |
— |
|
Rehabilitation of Drainage System, Barangay Bagumbayan, Quezon City
Natapos
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱29,381,895 |
100% |
2023-02-17 |
— |
|
Rehabilitation of Drainage System at Xavierville AVE., Quezon City
Natapos
SDG 11SDG 13
|
R2CG Builders INC. (Formerly: Rrcg 8639 Builders INC.) |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱18,971,780 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Drainage System at Scout Borromeo ST., Quezon City
Natapos
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱19,539,984 |
100% |
2019-07-12 |
— |
|
Rehabilitation of Drainage System at K-6TH Street, Barangay Kamuning, Quezon City
Natapos
SDG 11SDG 13
|
LIM General Contractor Corporation |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱19,597,931 |
100% |
2023-03-13 |
— |
|
Rehabilitation of Drainage System] at Barangay Batasan Hills, Quezon City
Natapos
SDG 11SDG 13
|
C & F Construction & Development Corporation |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱57,372,518 |
100% |
2024-03-18 |
— |
|
Rehabilitation of Drainage System at Barangay Amihan, Quezon City
Natapos
SDG 11SDG 13
|
Rworkmate Construction |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱4,741,678 |
100% |
2022-02-09 |
— |
|
Rehabilitation of Drainage, Sauyo Road, Quezon City
Natapos
SDG 11SDG 13
|
R.A. Pahati Const. & Supply, INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱47,529,245 |
100% |
2020-01-23 |
— |
|
Rehabilitation of Drainage Road 3 (PAG-ASA), Quezon City
Natapos
SDG 11SDG 13
|
Triches Construction & Trading |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱9,505,766 |
100% |
2022-02-14 |
— |
|
Rehabilitation of Drainage Road 2, Quezon City
Natapos
SDG 11SDG 13
|
Triches Construction & Trading |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱9,799,222 |
100% |
2022-02-14 |
— |
|
Rehabilitation of Drainage Road 1 (PAG - ASA) , Quezon City
Natapos
SDG 11SDG 13
|
Triches Construction & Trading |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱19,011,922 |
100% |
2020-01-23 |
— |
|
Rehabilitation of Drainage, Patsinador/ Riverside, Quezon City
Natapos
SDG 11SDG 13
|
Rend Enterprises & General Contractor |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱47,529,903 |
100% |
2020-01-23 |
— |
|
Rehabilitation of Drainage, Palawan ST., Quezon City
Natapos
SDG 11SDG 13
|
A.J. Lava Builders Corp. (Formerly: A.J. Lava Buil |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱19,010,040 |
100% |
2020-11-24 |
— |
|
Rehabilitation of Drainage, MH DEL Pilar, Quezon City
Natapos
SDG 11SDG 13
|
Rend Enterprises & General Contractor |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱47,529,903 |
100% |
2020-01-23 |
— |
|
Rehabilitation of Drainage, Mariblo Creek, Quezon City
Natapos
SDG 11SDG 13
|
Framecon Builders |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱29,596,000 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Drainage Malambo, Quezon City
Natapos
SDG 11SDG 13
|
Framecon Builders |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱9,505,932 |
100% |
2020-01-23 |
— |
|
Rehabilitation of Drainage Main, Barangay Central, Quezon City
Natapos
SDG 11SDG 13
|
11-16 Construction |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱19,597,198 |
100% |
2024-02-08 |
— |