Construction of Flood Mitigation Structure along Marikina River, STA. 20+800 to STA. 20+900, Barangay Bagong Silangan, Quezon City
Isinasagawa
SDG 11SDG 13
|
Triple 8 Construction & Supply, INC. (Formerly Triple 8 Const. & Supply) / Pilastro Builders & Development INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱95,519,116 |
97% |
2024-03-18 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 6, Barangay Bagumbayan, Quezon City
Isinasagawa
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱48,019,084 |
19% |
2025-05-23 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 5, Barangay Bagumbayan, Quezon City
Isinasagawa
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱48,019,084 |
19% |
2025-05-23 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 4, Barangay Bagumbayan, Quezon City
Isinasagawa
SDG 11SDG 13
|
MRB11 Construction Corporation (Formerly:MRB Cons |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱48,019,084 |
24% |
2025-05-23 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 3, Barangay Bagumbayan, Quezon City
Isinasagawa
SDG 11SDG 13
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱48,133,527 |
80% |
2025-05-23 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 2, Quezon City
Isinasagawa
SDG 11SDG 13
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱94,568,091 |
80% |
2025-02-20 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 2, Barangay Bagumbayan, Quezon City
Isinasagawa
SDG 11SDG 13
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱48,131,264 |
80% |
2025-05-23 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Phase 1, Quezon City
Isinasagawa
SDG 11SDG 13
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 2nd DEO |
Kontrol sa Baha at Drainage |
₱94,571,439 |
80% |
2025-02-20 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Barangay Batasan Hills, Quezon City
Natapos
SDG 11SDG 13
|
A.L. Salazar Construction, INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱96,499,650 |
100% |
2023-02-13 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Barangay Batasan Hills, Quezon City
Isinasagawa
SDG 11SDG 13
|
A.L. Salazar Construction, INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱190,353,410 |
97% |
2024-06-19 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Barangay Batasan Hills, Quezon City
Isinasagawa
SDG 11SDG 13
|
A.L. Salazar Construction, INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱189,139,794 |
40% |
2025-05-20 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Barangay Bagong Silangan, Quezon City
Natapos
SDG 11SDG 13
|
Triple 8 Construction & Supply, INC. (Formerly Triple 8 Const. & Supply) / Pilastro Builders & Development INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱96,499,630 |
100% |
2023-02-27 |
— |
|
Construction of Flood Mitigation Structure along Marikina River, Barangay Bagong Silangan, Quezon City
Isinasagawa
SDG 11SDG 13
|
Triple 8 Construction & Supply, INC. (Formerly Triple 8 Const. & Supply) / Pilastro Builders & Development INC. |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱95,524,983 |
61% |
2025-02-19 |
— |
|
Construction of Flood Mitigation Structure along Culiat Creek, Phase II, Barangay Bahay Toro, Quezon City
Isinasagawa
SDG 11SDG 13
|
Triple 8 Construction & Supply, INC. (Formerly Triple 8 Const. & Supply) |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱48,008,628 |
67% |
2025-02-19 |
— |
|
Construction of Flood Mitigating Structure at Dalton Pass, Brgy. Holy Spirit, Quezon City
Isinasagawa
SDG 11SDG 13
|
K84 Construction AND Development Corporation / EGB Construction Corporation (Formerly: EGB Construction) |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱48,509,956 |
11% |
2025-04-07 |
— |
|
Construction of Flood Mitigating Structure at Constabulatory RD. Brgy. Holy Spirit, Quezon City
Isinasagawa
SDG 11SDG 13
|
K84 Construction AND Development Corporation / EGB Construction Corporation (Formerly: EGB Construction) |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱48,509,954 |
11% |
2025-04-07 |
— |
|
Construction of Flood Mitigating Structure at Airforce Road RD. Brgy. Holy Spirit, Quezon City
Isinasagawa
SDG 11SDG 13
|
K84 Construction AND Development Corporation / EGB Construction Corporation (Formerly: EGB Construction) |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱97,019,950 |
5% |
2025-04-07 |
— |
|
Construction of Flood Mitigating Structure at AFP Road RD. Brgy. Holy Spirit, Quezon City
Isinasagawa
SDG 11SDG 13
|
K84 Construction AND Development Corporation / EGB Construction Corporation (Formerly: EGB Construction) |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱97,045,723 |
5% |
2025-04-07 |
— |
|
Construction of Flood Control Structure Within Barangay STA. Monica, Quezon City
Natapos
SDG 11SDG 13
|
Precious Construction / Darcy & Anna Builders & Trading |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱93,605,000 |
100% |
2022-05-19 |
— |
|
Construction of Flood Control Structure, Tullahan River, Barangay STA. Monica, Quezon City
Isinasagawa
SDG 11SDG 13
|
LE Bron Construction |
Quezon City 1st DEO |
Kontrol sa Baha at Drainage |
₱95,510,737 |
50% |
2025-02-19 |
— |