Rehabilitation of Culiat Creek, Brgy. OLD Balara, Quezon City
Completed
SDG 11SDG 13
|
Geecee Builders & Construction Supplies |
Quezon City 2nd DEO |
Flood control & drainage |
₱18,889,698 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Covered Court at Kasiyahan, Brgy. Holy Spirit, Quezon City
Ongoing
SDG 9
|
C.E.M. Construction, INC. |
Quezon City 1st DEO |
Buildings & facilities |
₱9,569,139 |
60% |
2023-11-09 |
— |
|
Rehabilitation of Commonwealth Multi-Purpose Building,Brgy. Commonwealth, Quezon City
Completed
SDG 9
|
Triches Construction & Trading |
Quezon City 1st DEO |
Buildings & facilities |
₱2,894,901 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Capoas Street, Brgy. Masambong, Quezon City
Completed
SDG 9SDG 11
|
Philippine Chemsteel Industries, INC. |
Quezon City 1st DEO |
Roads |
₱19,011,956 |
100% |
2021-03-01 |
— |
|
Rehabilitation of Camp Crame Road Network, Quezon City
Completed
SDG 9SDG 11
|
TJR Construction Corporation / Philippine Chemsteel Industries, INC. |
Quezon City 2nd DEO |
Roads |
₱47,040,256 |
100% |
2022-02-09 |
— |
|
Rehabilitation of Camp Aguinaldo Road Network, Package A, Quezon City
Ongoing
SDG 9SDG 11
|
Triple 8 Construction & Supply, INC. (Formerly Triple 8 Const. & Supply) |
Quezon City 2nd DEO |
Roads |
₱141,677,326 |
15% |
2025-05-23 |
— |
|
Rehabilitation of Buaya to Evangelista Creek, Quezon City
Completed
SDG 11SDG 13
|
V.S. Cerdon Iron Works & Construction |
Quezon City 2nd DEO |
Flood control & drainage |
₱2,846,492 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Buaya Creek, Quezon City
Completed
SDG 11SDG 13
|
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading |
Quezon City 2nd DEO |
Flood control & drainage |
₱4,851,553 |
100% |
2023-03-29 |
— |
|
Rehabilitation of Brgy. Hall Annex at Base 4, Brgy. Hall Annex at Base 4, Brgy. Commonwealth, Quezon City
Ongoing
SDG 9
|
Double Z Construction AND Supply |
Quezon City 1st DEO |
Buildings & facilities |
₱14,700,396 |
81% |
2023-04-26 |
— |
|
Rehabilitation of Benitez Building, UP College of Education, UP Diliman, Quezon City
Completed
SDG 9
|
Brentmin Roofing Enterprise |
Quezon City 2nd DEO |
Buildings & facilities |
₱4,726,796 |
100% |
2019-09-13 |
— |
|
Rehabilitation of Barangay Hall, Herminigildo Flores Building, Plaza ST., Brgy. Pansol, Quezon City
Completed
SDG 9
|
Metrics Construction & Trading |
Quezon City 2nd DEO |
Buildings & facilities |
₱2,847,291 |
100% |
2019-08-08 |
— |
|
Rehabilitation of Banlat Road, Quezon City
Completed
SDG 9SDG 11
|
Newbig Four J Construction INC. (Formerly: Four J Construction) |
Quezon City 1st DEO |
Roads |
₱9,598,943 |
100% |
2021-07-06 |
— |
|
Rehabilitation of Balon Bato Creek, Quezon City
Completed
SDG 11SDG 13
|
NEW Arcond Builders Incorporated (Formerly Arcond |
Quezon City 1st DEO |
Flood control & drainage |
₱19,012,000 |
100% |
2020-02-07 |
— |
|
Rehabilitation of Academic Multi-Purpose Building at University of the Philippines, Diliman, Quezon City
Completed
SDG 9
|
Alpha & Omega GEN. Contractor & Development Corp. ([Revoked] 38958) |
Quezon City 2nd DEO |
Buildings & facilities |
₱55,644,482 |
100% |
2019-09-13 |
— |
|
Rehabilitation of A 2-Storey Multipurpose Building, SAN Vicente, Quezon City
Completed
SDG 9
|
Quadrisquare Builders AND Trading |
Quezon City 2nd DEO |
Buildings & facilities |
₱5,939,940 |
100% |
2022-05-19 |
— |
|
Rehabilitation of 3-Storey Vanguard Building, University of the Philippines, Diliman, Quezon City
Completed
SDG 9
|
IM Construction Corporation |
Quezon City 2nd DEO |
Buildings & facilities |
₱39,199,148 |
100% |
2022-03-24 |
— |
|
Rehabilitation of 3 Storey, 12 Classroom, Balara Elementary School, Brgy. Pansol, Quezon City
Completed
SDG 4
|
ONE Euluz Construction Corporation (Formerly: Euluz Construction & Supply) |
Quezon City 2nd DEO |
Buildings & facilities |
₱4,696,404 |
100% |
2019-06-17 |
— |
|
Rehabilitation of 2-Storey, 6 Classroom School Building, Sumulong High School, Brgy. SAN Roque, Quezon City
Completed
SDG 4
|
Metrics Construction & Trading |
Quezon City 2nd DEO |
Buildings & facilities |
₱2,363,494 |
100% |
2019-06-17 |
— |
|
Rehabilitation / Major Repair of Permanent Bridges - Quezon AVE. BR. (B02333LZ) along Quezon AVE., Quezon City
Completed
SDG 9SDG 11
|
Alphatec Chemical Corporation |
Quezon City 2nd DEO |
Bridges |
₱19,574,784 |
100% |
2023-02-17 |
— |
|
Rehabilitation / Major Repair of Permanent Bridges; Mariablo BR. (B02335LZ) along E Rodriguez SR, Quezon City
Ongoing
SDG 9SDG 11
|
Eight J'S Construction Services / R-S Construction |
Quezon City 2nd DEO |
Bridges |
₱70,909,161 |
25% |
2025-04-11 |
— |