Showing 2701 to 2720 of 2747 projects. Download as CSV

Project Contractor Agency Type Budget Progress Started Target date
Road and Drainage Improvement of Quirino Highway and Peripheral Roads, Brgy. Gulod, Quezon City
Completed SDG 9SDG 11
Kennedy Energy AND Development Corp. Quezon City 1st DEO Roads ₱14,357,980 100% 2020-08-18 —
Road Improvement at Lakandula Extension, Roces ST., Apacible ST., Aguinaldo ST., Agoncillo ST., Shuster ST., and Lakandula ST., University of the Philippines, Diliman, Quezon City
Completed SDG 9SDG 11
MRB11 Construction Corporation (Formerly:MRB Cons Quezon City 2nd DEO Roads ₱46,451,846 100% 2018-02-02 —
Road Improvement Barangay Nagkaisang Nayon, Quezon City
Completed SDG 9SDG 11
E.L. Torres Construction AND Trading INC. (Formerly : E. L. Torres Construction & Trading Quezon City 1st DEO Roads ₱14,404,500 100% 2022-01-10 —
Road Improvement, Barangay SAN Agustin, Quezon City
Completed SDG 9SDG 11
5-1 Construction Corporation Quezon City 1st DEO Roads ₱9,591,867 100% 2022-01-10 —
Road Improvement BF Road, SAN Simon and STA. Catalina Street, Brgy. Holy Spirit, Quezon City
Completed SDG 9SDG 11
C & F Construction & Development Corporation Quezon City 1st DEO Roads ₱9,405,000 100% 2019-07-25 —
Road Improvement Katuparan Street Commonwealth, Quezon City
Completed SDG 9SDG 11
C & F Construction & Development Corporation Quezon City 1st DEO Roads ₱9,405,721 100% 2019-07-25 —
Road Improvement Molave Street, Brgy. Payatas Near GK, Quezon City
Completed SDG 9SDG 11
5-1 Construction Corporation Quezon City 1st DEO Roads ₱1,930,500 100% 2020-09-23 —
Road Improvement of Bernardo Street, Barangay Mariblo, Quezon City
Completed SDG 9SDG 11
Carry-ON Construction Quezon City 1st DEO Roads ₱9,509,153 100% 2022-02-16 —
Road Improvement of Fairlane Street, Quezon City
Completed SDG 9SDG 11
L.M.G. Construction Incorporated (Formerly: LMG Construction) Quezon City 1st DEO Roads ₱18,326,248 100% 2017-10-02 —
Road Improvement Phase 1, Lupang Pangako, Brgy. Payatas, Quezon City
Completed SDG 9SDG 11
5-1 Construction Corporation Quezon City 1st DEO Roads ₱4,826,250 100% 2020-09-23 —
Road Rehabilitation and Improvement at Tandang Sora Avenue, Quezon City
Completed SDG 9SDG 11
C & F Construction & Development Corporation Quezon City 1st DEO Roads ₱57,899,606 100% 2024-04-29 —
Road Upgrading of Debussy-Beethoven Street, Ideal Commonwealth Avenue, Fairview, Quezon City
Completed SDG 9SDG 11
CFC Fiber Construction Corporation Quezon City 1st DEO Roads ₱14,779,890 100% 2020-11-24 —
Road Widening: Bonny Serrano (R00854LZ) - K0010 + (-770) - K0010 + 104, K0010 + 880 - K0011 + 100, Quezon City
Completed SDG 9SDG 11
IM Construction Corporation Quezon City 2nd DEO Roads ₱20,769,762 100% 2024-02-23 —
ROW - Naia Expressway Project Paved (Concrete) TO Paved (Concrete)
Ongoing Approximate location SDG 9SDG 11
— Regional Office Roads ₱1,000,000,000 — — —
ROW of the construction of Longos Creek Drainage Channel Improvement Right-OF-WAY
Completed Approximate location SDG 11SDG 13
By Administration Malabon-Navotas District Engineering Office Flood control & drainage ₱9,374,000 100% 2011-02-01 2012-12-31
ROW of the Construction of Polder Dike Right-OF-WAY
Completed Approximate location SDG 11SDG 13
By Administration Malabon-Navotas District Engineering Office Flood control & drainage ₱12,099,000 100% 2003-02-01 2012-12-31
ROW of the Construction of Regulation Ponds (along Gov. Pascual Brgy. Catmon Malabon City) Right-OF-WAY
Completed Approximate location SDG 9SDG 11
By Administration Malabon-Navotas District Engineering Office Roads ₱4,544,000 100% 2011-02-01 2012-12-31
Site Development for the UP Diliman Union Building, Quezon City
Ongoing SDG 9
Devex Incorporated Quezon City 2nd DEO Buildings & facilities ₱14,468,873 0% 2021-08-27 —
Site Development, Multi-Purpose Pavement Including Drainage Improvement at Carlos Albert, Barangay Santol, Quezon City
Completed SDG 9
Dimaguila Construction & Supply, INC. Quezon City 2nd DEO Buildings & facilities ₱2,853,736 100% 2019-06-17 —
Slope Protection Works at Tanza Polder Dike Leading to the North Navotas Pumping Station using Bioengineering Construction
Completed Approximate location SDG 11SDG 13
Edison Development Construction Malabon-Navotas District Engineering Office Flood control & drainage ₱50,361,000 100% 2014-03-21 2015-01-22