| CONSTRUCTION of FOUR (4) STOREY MULTI-PURPOSE BUILDING at DON FABIAN ST., BRGY. COMMONWEALTH, QUEZON CITY |
Ongoing |
70% |
₱29,556,928 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, PURA V. KALAW ELEMENTARY SCHOOL, BRGY. MILAGROSA, QUEZON CITY |
Ongoing |
31% |
₱28,783,658 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, DON QUINTIN PAREDES, SR. HIGH SCHOOL, BARANGAY QUIRINO 2-B, QUEZON CITY |
Ongoing |
31% |
₱24,757,905 |
Quezon City 2nd DEO |
| CONSTRUCTION of THREE (3) STOREY BUREAU of RESEARCH & STANDARDS (BRS) PHYSICAL LABORATORY BUILDING, PHASE 3 WITHIN DPWH REGION IV-A COMPOUND, EDSA, QUEZON CITY |
Completed |
100% |
₱24,498,977 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, CAMP AGUINALDO, QUEZON CITY |
Completed |
100% |
₱24,006,903 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (PHASE II) at BELARMINO SENIORHIGH SCHOOL, BARANGAY MILAGROSA, QUEZON CITY |
Ongoing |
34% |
₱19,185,907 |
Quezon City 2nd DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY MARILAG, QUEZON CITY |
Completed |
100% |
₱18,990,542 |
Quezon City 2nd DEO |
| REHABILITATION of ROAD INCLUDING DRAINAGE ACME STREET, BARANGAY SAN BARTOLOME, QUEZON CITY |
Completed |
100% |
₱18,815,856 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, KANLAON BUILDING at NICA COMPOUND (PHASE 2), QUEZON CITY |
Completed |
100% |
₱14,473,651 |
Quezon City 2nd DEO |
| REHABILITATION of OPTICAL MEDIA BOARD BUILDING, QUEZON CITY |
Ongoing |
1% |
₱11,399,315 |
Quezon City 2nd DEO |
| REHABILITATION of MPB (COVERED COURT) BRGY. LAGRO, QUEZON CITY |
Completed |
100% |
₱11,289,600 |
Quezon City 1st DEO |
| IMPROVEMENT of ROAD and DRAINAGE in MORENA BLANCO ST. in BRGY. STA. MONICA, QUEZON CITY |
Completed |
100% |
₱9,897,540 |
Quezon City 1st DEO |
| IMPROVEMENT of ROAD and DRAINAGE in SIERRA MADRE ST. in BRGY. KALIGAYAHAN, QUEZON CITY |
Ongoing |
73% |
₱9,800,310 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (COVERED COURT) in CHAMPACA, BARANGAY PASONG PUTIK, NOVALICHES, QUEZON CITY |
Completed |
100% |
₱9,702,000 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (PATHWALK) at BARANGAY STA. LUCIA, NOVALICHES, QUEZON CITY |
Completed |
100% |
₱9,701,353 |
Quezon City 1st DEO |
| REHABILITATION (COMPLETION) of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, BARANGAY MARILAG, QUEZON CITY |
Completed |
100% |
₱9,593,989 |
Quezon City 2nd DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING, XAVIERVILLE I, BARANGAY LOYOLA HEIGHTS, QUEZON CITY |
Ongoing |
82% |
₱9,593,123 |
Quezon City 2nd DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), BRGY. OLD BALARA, QUEZON CITY |
Completed |
100% |
₱9,585,548 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI - PURPOSE BUILDING at MARINE STREET, CORNER RANGER STREET, BARANGAY HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱7,843,151 |
Quezon City 1st DEO |
| REHABILITATION of ROAD, BARANGAY DON MANUEL, PHASE II, QUEZON CITY |
Completed |
100% |
₱7,812,937 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at LOVINGFUL STREET, BARANGAY BAGONG SILANGAN, QUEZON CITY |
Completed |
100% |
₱6,860,561 |
Quezon City 1st DEO |
| CONSTRUCTION/REHABILITATION of MPB BRGY. NORTH FAIRVIEW, QUEZON CITY |
Completed |
100% |
₱5,703,600 |
Quezon City 1st DEO |
| REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - PRIMARY ROADS: C-5 ROAD - K0013 + 800 - K0013 + 944, QUEZON CITY |
Ongoing |
86% |
₱5,116,770 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING BRGY. STA. LUCIA, QUEZON CITY |
Completed |
100% |
₱4,900,500 |
Quezon City 1st DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY STA. LUCIA, QUEZON CITY |
Ongoing |
61% |
₱4,859,328 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BRGY. GREATER LAGRO, QUEZON CITY |
Completed |
100% |
₱4,849,821 |
Quezon City 1st DEO |
| CONSTRUCTION / REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY STA. LUCIA, QUEZON CITY |
Completed |
100% |
₱4,816,842 |
Quezon City 1st DEO |
| REHABILITATION of MULTI-PURPOSE in BARANGAY STA. MONICA, NOVALICHES, QUEZON CITY |
Completed |
100% |
₱4,801,403 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY KALIGAYAHAN, QUEZON CITY |
Completed |
100% |
₱4,801,393 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING BRGY.KALIGAYAHAN, QUEZON CITY |
Completed |
100% |
₱4,801,379 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BRGY. LAGRO, QUEZON CITY |
Completed |
100% |
₱4,801,340 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BRGY STA. MONICA, QUEZON CITY |
Completed |
100% |
₱4,801,291 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BRGY. STA. LUCIA, QUEZON CITY |
Completed |
100% |
₱4,801,136 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY LAGRO, QUEZON CITY |
Completed |
100% |
₱1,913,739 |
Quezon City 1st DEO |