← Top Contractors
PERRC INC. (FORMERLY: P.E.R.R.C. CONSTRUCTION & DEVELOPMENT CORPORATION)
- Projects
- 19
17 completed, 2 ongoing, 0 upcoming
- Total budget
- ₱314,963,505
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| REPAIR/ REHABILITATION/ UPGRADING of REGALADO SOUTH, QUEZON CITY, from FAIRVIEW to REGALADO AVENUE, QUEZON CITY |
Completed |
100% |
₱93,553,446 |
Quezon City 1st DEO |
| CONSTRUCTION / REHABILITATION of FLOOD CONTROL STRUCTURES at LUMBAN CREEK, BARANGAY MATANDANG BALARA, QUEZON CITY |
Completed |
100% |
₱48,985,157 |
Quezon City 2nd DEO |
| REHABILITATION of MULTIPURPOSE BUILDING (SCHOOL of ECONOMICS) at U.P. DILIMAN, QUEZON CITY |
Ongoing |
40% |
₱26,731,913 |
National Capital Region |
| IMPROVEMENT / COMPLETION / CONSTRUCTION of MULTIPURPOSE BUILDING, BRGY. PALIGSAHAN, QUEZON CITY |
Completed |
100% |
₱19,596,377 |
Quezon City 2nd DEO |
| IMPROVEMENT of MULTI-PURPOSE BUILDING, BARANGAY PALIGSAHAN, QUEZON CITY |
Completed |
100% |
₱9,898,000 |
Quezon City 2nd DEO |
| REHABILITATION of ROAD at PHILAM HOMES, WEST TRIANGLE, QUEZON CITY |
Completed |
100% |
₱9,604,638 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION of MULTI-PURPOSE BUILDING at BRGY. LOURDES, QUEZON CITY |
Completed |
100% |
₱9,597,666 |
Quezon City 1st DEO |
| CONSTRUCTION/ IMPROVEMENT of MULTI-PURPOSE BUILDING, PROJECT 6, QUEZON CITY |
Completed |
100% |
₱9,583,006 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at NON-SCHOOL for CRIPPLED CHILDREN (COVERED COURT), BRGY. LOURDES, QUEZON CITY |
Completed |
100% |
₱9,552,006 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (LIVELIHOOD and TRAINING CENTER) at BARANGAY VASRA, QUEZON CITY |
Completed |
100% |
₱9,506,057 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BARABGAY WEST TRIANGLE, QUEZON CITY |
Completed |
100% |
₱9,494,882 |
Quezon City 1st DEO |
| REBANILITATION of MULTI-PURPOSE BUILDING at BARANGAY DAMAR, QUEZON CITY |
Completed |
100% |
₱9,480,743 |
Quezon City 1st DEO |
| IMPROVEMENT/ REHABILITATION of ROAD at WEST TRIANGLE, QUEZON CITY |
Completed |
100% |
₱9,405,996 |
Quezon City 1st DEO |
| REHABILITATION of ROAD with DRAINAGE INPROVEMENT at BARANGAY TALAYAN, QUEZON CITY |
Completed |
100% |
₱8,805,956 |
Quezon City 1st DEO |
| REHABILITATION of MULTI - PURPOSE BUILDING (BARANGAY HALL), BARANGAY WEST TRIANGLE, QUEZON CITY |
Completed |
100% |
₱6,860,418 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BRGY. PALIGSAHAN, QUEZON CITY |
Completed |
100% |
₱6,853,636 |
Quezon City 2nd DEO |
| CONSTRUCTION with SITE DEVELOPMENT of MULTI-PURPOSE BUILDING at BARANGAY MAHARLIKA, QUEZON CITY |
Completed |
100% |
₱6,722,100 |
Quezon City 1st DEO |
| CONSTRUCTION (COMPLETION) of MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY WEST TRIANGLE, QUEZON CITY |
Ongoing |
87% |
₱5,820,840 |
Quezon City 1st DEO |
| CONSTRUCTION / REHABILITATION of MULTI-PURPOSE BUILDING, PALIGSAHAN, QUEZON CITY |
Completed |
100% |
₱4,910,667 |
Quezon City 2nd DEO |