← Top Contractors
NUEDA BUILDERS CONSTRUCTION & SUPPLY INC.
- Projects
- 15
13 completed, 2 ongoing, 0 upcoming
- Total budget
- ₱264,661,654
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| REHABILITATION of ROAD at BARANGAY BAGONG SILANGAN, QUEZON CITY |
Completed |
100% |
₱37,632,071 |
Quezon City 1st DEO |
| REHABILITATION of ROAD with DRAINAGE IMPROVEMENT at MIRA NILA HOMES, BRGY. PASONG TAMO, QUEZON CITY |
Ongoing |
58% |
₱28,808,870 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURE at BARABGAY TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱20,166,300 |
Quezon City 1st DEO |
| REHABILITATION of ROAD and DRAINAGE IMPROVEMENT, BONIFACIO VILLAGE, BARANGAY PASONG TAMO, QUEZON CITY |
Completed |
100% |
₱19,599,969 |
Quezon City 1st DEO |
| REHABIILITATION of ROAD and DRAINAGE IMPROVEMENT, MIRA NILA HOMES, BARANGAY PASONG TAMO, QUEZON CITY |
Completed |
100% |
₱19,599,959 |
Quezon City 1st DEO |
| REHABILITATION of ROAD with DRAINAGE IMPROVEMENT at INTERVILLE II, BRGY. CULIAT, QUEZON CITY |
Ongoing |
19% |
₱19,202,505 |
Quezon City 1st DEO |
| REHABILITATION of DRAINAGE BANLAT ROAD, QUEZON CITY |
Completed |
100% |
₱19,011,508 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURE at MACEDA BRIDGE, BARANGAY TALIPAPA, QUEZON CITY |
Completed |
100% |
₱19,006,235 |
Quezon City 1st DEO |
| IMPROVEMENT/ REHABILITATION of DRAINAGE SYSTEM at 11TH JAMBOREE ST., QUEZON CITY |
Completed |
100% |
₱14,649,477 |
Quezon City 2nd DEO |
| WIDENING of ROAD and DRAINAGE IMPROVEMENT of 11TH JAMBOREE ST., QUEZON CITY |
Completed |
100% |
₱14,633,280 |
Quezon City 2nd DEO |
| REHABILITATION/ IMPROVEMENT of ROAD at BONIFACIO, BRGY. PASONG TAMO, QUEZON CITY |
Completed |
100% |
₱14,258,976 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, MIRA NILA HOMES, BARANGAY PASONG TAMO, QUEZON CITY |
Completed |
100% |
₱9,899,951 |
Quezon City 1st DEO |
| CONCRETING of 11TH JAMBOREE ST., QUEZON CITY |
Completed |
100% |
₱9,614,858 |
Quezon City 2nd DEO |
| REHABILITATION of ROAD at SAUYO ROAD, BARANGAY SAUYO, QUEZON CITY |
Completed |
100% |
₱9,310,000 |
Quezon City 1st DEO |
| WIDENING of ROAD and DRAINAGE IMPROVEMENT of EUGENIO LOPEZ DRIVE, QUEZON CITY |
Completed |
100% |
₱9,267,696 |
Quezon City 2nd DEO |