← Top Contractors
MSV CONSTRUCTION AND SUPPLIES
- Projects
- 9
9 completed, 0 ongoing, 0 upcoming
- Total budget
- ₱151,718,486
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| REHABILITATION of FLOOD CONTROL STRUCTURE of BARANGAY SAN BARTOLOME (PHASE 2), QUEZON CITY |
Completed |
100% |
₱48,990,596 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, GOVERNMENT CENTER, BARANGAY BAGBAG, QUEZON CITY |
Completed |
100% |
₱28,517,956 |
Quezon City 1st DEO |
| CONSTRUCTION of LAGRO MULTI-PURPOSE BUILDING (FIRE DEPARTMENT), QUEZON CITY |
Completed |
100% |
₱14,699,850 |
Quezon City 1st DEO |
| CONSTRUCTION of FAIRVIEW MULTI-PURPOSE BUILDING (FIRE DEPARTMENT), QUEZON CITY |
Completed |
100% |
₱14,692,265 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONROL STRUCTURE at BARANGAY BAESA, QUEZON CITY |
Completed |
100% |
₱14,260,636 |
Quezon City 1st DEO |
| CONSTRUCTION (COMPLETION) of MULTI-PURPOSE BUILDING, BARANGAY STA MONICA, QUEZON CITY |
Completed |
100% |
₱9,603,000 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY TALIPAPA, QUEZON CITY |
Completed |
100% |
₱9,505,908 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY TALIPAPA, QUEZON CITY |
Completed |
100% |
₱6,654,200 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (PHASE I), BARANGAY SAN AGUSTIN, QUEZON CITY |
Completed |
100% |
₱4,794,075 |
Quezon City 1st DEO |