Projects
15 10 completed, 5 ongoing, 0 upcoming
Total budget
₱412,442,536
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
REHABILITATION of ROADS, BARANGAY MATANDANG BALARA, PHASE III, QUEZON CITY Ongoing 91% ₱47,491,616 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY UGONG NORTE, PHASE III, QUEZON CITY Ongoing 36% ₱45,125,159 Quezon City 2nd DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURES and TRIBUTARIES along CULIAT CREEK (LEFT SIDE) BARANGAY TORO, QUEZON CITY Completed 100% ₱42,777,000 Quezon City 1st DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURES and TRIBUTARIES along SAN FRANCISCO RIVER, PHASE I, QUEZON CITY Completed 100% ₱42,731,524 Quezon City 1st DEO
REHABILITATION of FLOOD MITIGATION STRUCTURE along SAN JUAN RIVER, QUEZON CITY (PHASE XVI) Completed 100% ₱41,285,159 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, BRGY. UGONG NORTE, QUEZON CITY Completed 100% ₱39,197,892 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, BARANGAY QUIRINO 2B, QUEZON CITY Completed 100% ₱38,451,638 Quezon City 2nd DEO
REHABILITATION of ROAD, BARANGAY WEST KAMIAS, QUEZON CITY Ongoing 31% ₱29,091,091 Quezon City 2nd DEO
REHABILITATION of ROAD, BARANGAY MATANDANG BALARA, PHASE II, QUEZON CITY Completed 100% ₱27,584,184 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, BRGY. WHITE PLAINS, QUEZON CITY Ongoing 0% ₱19,393,048 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY UGONG NORTE, PHASE II QUEZON CITY Ongoing 52% ₱12,479,620 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING (MORTUARY), BARANGAY BAGUMBAYAN, QUEZON CITY Completed 100% ₱9,600,243 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING (PHASE 2) at BARANGAY STO. CRISTO, QUEZON CITY Completed 100% ₱9,506,000 Quezon City 1st DEO
REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY VETERANS VILLAGE, QUEZON CITY Completed 100% ₱4,850,840 Quezon City 1st DEO
CONSTRUCTION (COMPLETION) of MULTI-PURPOSE BUILDING, BRGY. BAGUMBUHAY, QUEZON CITY(PHASE III) Completed 100% ₱2,877,522 Quezon City 2nd DEO