KENNEDY ENERGY AND DEVELOPMENT CORP.
- Projects
- 4 4 completed, 0 ongoing, 0 upcoming
- Total budget
- ₱52,867,350
- Citizen rating
- Not yet rated
- Finished on time
- No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
If something here is wrong, tell us through the contact form.
Reply as this contractorDraft for review: this explanation has not yet been checked by an expert.
Projects
| Project | Status | Progress | Budget | Agency |
|---|---|---|---|---|
| STRUCTURAL IMPROVEMENT of PUBLIC BUILDINGS and CONSTRUCTION of EVACUATION CENTER, NATIONAL CAPITAL REGION, CUBAO ELEMENTARY SCHOOL, COSETENG BUILDING, QUEZON CITY | Completed | 100% | ₱14,942,154 | Quezon City 2nd DEO |
| ROAD and DRAINAGE IMPROVEMENT of QUIRINO HIGHWAY and PERIPHERAL ROADS, BRGY. GULOD, QUEZON CITY | Completed | 100% | ₱14,357,980 | Quezon City 1st DEO |
| ROAD and DRAINAGE IMPROVEMENT of P. DELA CRUZ ROAD, SAN BARTOLOME, QUEZON CITY | Completed | 100% | ₱13,965,000 | Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at NEW HAVEN PARK, CAMILO OASIS CORNER BACNOTAN STREET NEW HEAVEN VILLAGE, BRGY. KALIGAYAHAN , QUEZON CITY | Completed | 100% | ₱9,602,216 | Quezon City 1st DEO |