← Top Contractors
JJPR CONSTRUCTION SERVICES
- Projects
- 9
6 completed, 3 ongoing, 0 upcoming
- Total budget
- ₱668,056,483
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| REHABILITATION of ROAD, BARANGAY UGONG NORTE, PACKAGE 2, QUEZON CITY |
Ongoing |
56% |
₱141,819,591 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENANCE - TERTIARY ROADS: E RODRIGUEZ SR - K0006 + (-597) - K0006 + 835, QUEZON CITY |
Completed |
100% |
₱94,531,239 |
Quezon City 2nd DEO |
| REHABILITATION of DRAINAGE SYSTEM, BARANGAY SOUTH TRIANGLE, QUEZON CITY |
Completed |
100% |
₱72,367,299 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENANCE - PRIMARY ROADS: E RODRIGUEZ JR AVE - K0012 + (-512) - K0012 + 612, QUEZON CITY |
Ongoing |
95% |
₱66,190,452 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENANCE - TERTIARY ROADS: TOMAS MORATO - K0009 + (-091) - K0009 + 1593, QUEZON CITY |
Completed |
100% |
₱66,189,479 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENANCE - TERTIARY ROADS: E RODRIGUEZ SR - K0007 + (-250) - K0007 + 472, QUEZON CITY |
Ongoing |
80% |
₱66,173,624 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENACE - PRIMARY ROADS: E RODRIGUEZ JR AVE - K0012 + (-621) - K0012 + 105, QUEZON CITY |
Completed |
100% |
₱64,287,112 |
Quezon City 2nd DEO |
| REHABILITATION of DRAINAGE SYSTEM, BARANGAY PINYAHAN, QUEZON CITY |
Completed |
100% |
₱48,249,355 |
Quezon City 2nd DEO |
| REHABILITATION of DRAINAGE SYSTEM, BARANGAY TATALON, QUEZON CITY |
Completed |
100% |
₱48,248,332 |
Quezon City 2nd DEO |