Projects
20 16 completed, 4 ongoing, 0 upcoming
Total budget
₱209,947,697
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
CONSTRUCTION of MULTI-PURPOSE BUILDING (DISASTER OPERATIONS CENTER) at BARANGAY PASONG TAMO, QUEZON CITY Completed 100% ₱29,399,870 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING 1, BARANGAY CULIAT, QUEZON CITY Completed 100% ₱29,399,440 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY SAUYO (KABAHAGI), QUEZON CITY Ongoing 86% ₱19,403,978 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY PASONG TAMO, QUEZON CITY Ongoing 0% ₱19,401,088 Quezon City 1st DEO
CONSTRUCTION of DRAINAGE SYSTEMS at BRGY. PASONG TAMO, QUEZON CITY Completed 100% ₱19,203,941 Quezon City 1st DEO
CONSTRUCTION (COMPLETION) of MULTI-PURPOSE BUILDING at NEW HAVEN, BARANGAY KALIGAYAHAN, QUEZON CITY Ongoing 84% ₱14,567,509 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING BARANGAY STA. LUCIA, QUEZON CITY Completed 100% ₱9,799,916 Quezon City 1st DEO
REHABILITATION of DRAINAGE and ROAD at TANDANG SORA AVE., BRGY. TANDANG SORA, QUEZON CITY Completed 100% ₱9,505,775 Quezon City 1st DEO
CONSTRUCTION of ROAD INCLUDING DRAINAGE IMPROVEMENT at BARANGAY CULIAT, QUEZON CITY Completed 100% ₱8,800,000 Quezon City 1st DEO
REHABILITATION of SCHOOL BUILDING at BARANGAY SANGANDAAN, QUEZON CITY Completed 100% ₱6,721,575 Quezon City 1st DEO
REHABILITATION and DRAINAGE IMPROVEMENT of ROADS BARANGAY BALON BATO, QUEZON CITY Completed 100% ₱6,654,156 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING at JEM 7, BARANGAY TALIPAPA, QUEZON CITY Completed 100% ₱6,621,521 Quezon City 1st DEO
REHABILITATION of MULTI-PURPOSE BUILDING, BRGY. HOLY SPIRIT, QUEZON CITY Completed 100% ₱5,758,724 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY PASONG TAMO, QUEZON CITY PHASE I Completed 100% ₱4,899,886 Quezon City 1st DEO
REHABILITATION of FLOOD CONTROL STRUCTURE at BARANGAY SAN AGUSTIN, QUEZON CITY Ongoing 26% ₱4,848,137 Quezon City 1st DEO
CONSTRUCTION of COVERED COURT at PUROK PAG-ASA, QUEZON CITY Completed 100% ₱4,847,621 Quezon City 1st DEO
CONSTRUCTION/ REHABILITATION of MAPALAD HOA MULTI-PURPOSE BUILDING with COVERT COURT, BRGY. COMMONWEALTH, QUEZON CITY Completed 100% ₱3,880,337 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of ROAD: CONCRETE REBLOCKING along CLOVERLEAF (SO5131LZ) CHAINAGE 0 - CHAINAGE 234, QUEZON CITY Completed 100% ₱3,555,868 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of ROAD : ASPHALT OVERLAY - along CLOVERLEAF (SO5176LZ) CHAINAGE 0 - CHAINAGE 215, QUEZON CITY Completed 100% ₱1,669,669 Quezon City 1st DEO
INSTALLATION of SIGNAGE-WARNING, ADVISORY and REGULATORY SIGNS and PAVEMENT MARKINGS along EPIFANIO DELOS SANTOS AVE. (EDSA) - K0014 + 223 - K0015 + 318, MASAMBONG, QUEZON CITY, METRO MANILA Completed 100% ₱1,008,686 Quezon City 1st DEO