Projects
51 38 completed, 13 ongoing, 0 upcoming
Total budget
₱2,399,435,941
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
PREVENTIVE MAINTENANCE - SECONDARY ROADS - COMMONWEALTH AVE - K0020 + 520 - K0017 + 061, QUEZON CITY Completed 100% ₱181,335,446 Quezon City 1st DEO
PREVENTIVE MAINTENANCE - COMMONWEALTH AVE (LUZON AVE to CENTRAL AVE), QUEZON CITY Completed 100% ₱144,749,260 Quezon City 1st DEO
REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - PAYATAS RD - K0022+(-1067) - K0022+000, K0025+230 - K0026+500, QUEZON CITY Completed 100% ₱144,748,756 Quezon City 1st DEO
CONSTRUCTION of KATIPUNAN AVE., EXTENSION (MWSS PROPERTY to GSIS PROPERTY), QUEZON CITY Completed 100% ₱131,450,993 Quezon City 1st DEO
REHABILITATION/ RECONSTRUCTION/ UPGRADING of DAMAGED PAVED ROADS - TERTIARY ROADS - DEL MONTE AVE., K0008+680 - K0010+604.40, QUEZON CITY Completed 100% ₱96,499,514 Quezon City 1st DEO
REHABILITATION/ RECONSTRUCTION/ UPGRADING of DAMAGED PAVED ROADS - TERTIARY ROADS - BATASAN ROAD - K0018+000 - K0019+765, QUEZON CITY Completed 100% ₱96,499,208 Quezon City 1st DEO
REHABILITATION / RECONSTRUCTION/ UPGRADING of DAMAGED PAVED ROADS - TERTIARY ROADS - AGHAM ROAD - K0011+(-610) - K0011+250, K0011+(-252) - K0011+602, QUEZON CITY Completed 100% ₱96,499,151 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of ROAD: ASPHALT OVERLAY - LUZON AVENUE (S05625LZ) - CHAINAGE 0 - CHAINAGE 1047, QUEZON CITY Completed 100% ₱96,498,953 Quezon City 1st DEO
REHABILITATION/RECONSTRUCTION/UPGRADING of DAMAGED PAVED ROADS - SECONDARY ROADS - COMMONWEALTH AVENUE (S05646LZ) - K0018+250 - K0018+730, QUEZON CITY Ongoing 99% ₱96,039,421 Quezon City 1st DEO
CONSTRUCTION of SLOPE PROTECTION STRUCTURE along MARIKINA RIVER (STA. 19+550 to 19+700), BRGY. BATASAN HILLS, QUEZON CITY Completed 100% ₱95,079,478 Quezon City 1st DEO
REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - SECONDARY ROADS: COMMONWEALTH AVE - K0013 + 400 - K0013 + 820, QUEZON CITY Ongoing 35% ₱94,378,553 Quezon City 2nd DEO
REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - SECONDARY ROADS: COMMONWEALTH AVE - K0013 + 820 - K0014 + 240, QUEZON CITY Ongoing 37% ₱94,377,568 Quezon City 2nd DEO
CONSTRUCTION/ UPGRADING/ REHABILITATION of DRAINAGE along QUIRINO HI-WAY K0010+(-127) - K0014+294, QUEZON CITY Completed 100% ₱74,999,891 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of MINDANAO AVE., K0018+(-092) - K0016+400, (SO5475LZ) CHAINAGE 000 - CHAINAGE496, (SO5476LZ) CHAINAGE 000 - CHAINAGE 496, K0015+800 - K0017+604, QUEZON CITY Completed 100% ₱70,335,625 Quezon City 1st DEO
REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - PRIMARY ROADS - CONGRESSIONAL AVENUE EXTENSION, QUEZON CITY Completed 100% ₱68,812,990 Quezon City 1st DEO
STRUCTURAL RETROFITTING of the DEPARTMENT of ENVIRONMENT and NATURAL RESOURCES (DENR) - CENTRAL OFFICE MAIN BUILDING, VISAYAS AVE., DILIMAN, QUEZON CITY Ongoing 41% ₱66,052,316 Quezon City 1st DEO
CONSTRUCTION of FLOOD MITIGATION STRUCTURES (VARSITY, EVERGREEN, MAPPLEWOOD) at BARANGAY PASONG TAMO, QUEZON CITY Ongoing 18% ₱54,821,360 Quezon City 1st DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURE at LUMBAN CREEK, BARANGAY MATANDANG BALARA, QUEZON CITY (PHASE III) Completed 100% ₱48,997,300 Quezon City 2nd DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURES and TRIBUTARIES, BRGY. COMMONWEALTH (PHASE 6), QUEZON CITY Completed 100% ₱48,089,367 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING (PUBLIC CIVIC CENTER), BRGY. NEW ERA, QUEZON CITY Ongoing 75% ₱47,767,500 Quezon City 1st DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURES and TRIBUTARIES,, BRGY. COMMONWEALTH (PHASE 5), QUEZON CITY Completed 100% ₱47,040,000 Quezon City 1st DEO
REHABILITATION of 3-STOREY VANGUARD BUILDING, UNIVERSITY of the PHILIPPINES, DILIMAN, QUEZON CITY Completed 100% ₱39,199,148 Quezon City 2nd DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURE, BARANGAY NEW ERA, QUEZON CITY Completed 100% ₱35,972,605 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of CONGRESSIONAL AVE., EXT. K0015+(-903) - K0016+813, K0016+(-794) - K0015+921, QUEZON CITY Completed 100% ₱35,245,184 Quezon City 1st DEO
CONSTRUCTION of ROADS INCLUDING FLOOD CONTROL STRUCTURES at BARANGAY BALINGASA, QUEZON CITY Ongoing 85% ₱29,402,978 Quezon City 1st DEO

Show all 51 projects