Elite General Contractor AND Development Corp.
- Projects
- 10
6 completed, 4 ongoing, 0 upcoming
- Total budget
- ₱522,167,035
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| Construction of National Tobacco Administration Building, Quezon City (Phase 3) (RE-Advertisement) |
Ongoing |
0% |
₱141,531,018 |
National Capital Region |
| Rehabilitation of Flood Mitigation Structure along SAN Juan River (Phase Lxii), Quezon City |
Ongoing |
16% |
₱94,556,651 |
Quezon City 2nd DEO |
| Construction of National Tobacco Administration Building, Quezon City (Phase 4) |
Ongoing |
0% |
₱94,425,702 |
National Capital Region |
| Construction (Completion) of the School of Urban and Regional Planning (Surp) Building, UP Diliman, Quezon City |
Ongoing |
73% |
₱56,726,211 |
National Capital Region |
| Rehabilitation of Flood Mitigation Structure along SAN Juan River (Phase Xxii), Quezon City |
Completed |
100% |
₱48,948,822 |
Quezon City 2nd DEO |
| Preventive Maintenance of Road: Concrete Reblocking - Epifanio Delos Santos AVE. (Edsa) (S05132LZ) - K0016 + (-239) - K0016 + (-006), K0016 + (-431) - K0016 + (-239), K0016 + (-536) - K0016 + (-431), K0016 + 1152 - K0017 + 252, K0016 .... Quezon City |
Completed |
100% |
₱28,223,395 |
Quezon City 2nd DEO |
| Construction of Multipurpose Building W/ Gymnasium, Brgy. Roxas, Quezon City |
Completed |
100% |
₱24,748,992 |
Quezon City 2nd DEO |
| Construction/ Rehabilitation/ Improvement of Multi-Purpose Building, Batasan Hills, Quezon City |
Completed |
100% |
₱17,963,234 |
Quezon City 1st DEO |
| Construction of Ballistic Testing Facility Inside Nhqcl Compound, Camp Bgen. Rafael T. Crame, Quezon City (RE-Advertisement) |
Completed |
100% |
₱11,177,743 |
National Capital Region |
| Construction of Multi-Purpose Facilities, SB Park, Barangay Tandang Sora, Quezon City |
Completed |
100% |
₱3,865,266 |
Quezon City 1st DEO |