← Top Contractors
EDELCRIZ CONSTRUCTION
- Projects
- 9
9 completed, 0 ongoing, 0 upcoming
- Total budget
- ₱64,860,307
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱19,206,000 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of MULTI-PURPOSE BUILDING at BARANGAY BAGONG SILANGAN, QUEZON CITY |
Completed |
100% |
₱19,007,475 |
Quezon City 1st DEO |
| CONSTRUCTION/IMPROVEMENT of MPB at SARET STREET, BRGY. BATASAN HILLS, QUEZON CITY |
Completed |
100% |
₱7,522,506 |
Quezon City 1st DEO |
| REHABILITATION of HOLY SPIRIT MULTI-PURPOSE BUILDING 2 BRGY. HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱3,821,150 |
Quezon City 1st DEO |
| CONSTRUCTION of HOLY SPIRIT MULTI-PURPOSE BUILDING 1, BRGY. HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱3,801,600 |
Quezon City 1st DEO |
| CONSTRUCTION of HOLY SPIRIT MULTI-PURPOSE BUILDING 2, BRGY. HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱3,801,600 |
Quezon City 1st DEO |
| CONSTRUCTION of MPB at NARRA STREET, BRGY. PAYATAS, QUEZON CITY |
Completed |
100% |
₱2,879,996 |
Quezon City 1st DEO |
| CONSTRUCTION of MPB, SAN LORENZO RUIZ STREET, BRGY. PAYATAS, QUEZON CITY |
Completed |
100% |
₱2,879,247 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI - PURPOSE BUILDING BRGY. PAYATAS, QUEZON CITY |
Completed |
100% |
₱1,940,732 |
Quezon City 1st DEO |