← Top Contractors
CARRY-ON CONSTRUCTION
- Projects
- 12
11 completed, 1 ongoing, 0 upcoming
- Total budget
- ₱110,964,343
- Citizen rating
-
Not yet rated
- Finished on time
-
No data
- Public reports
- 0
How to read these numbers
- Where the data comes from
- Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
- What a rating means
- A rating is the opinion of the residents who left it. It is not an audit.
- What a report means
- A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.
Draft for review: this explanation has not yet been checked by an expert.
Projects
| Project |
Status |
Progress |
Budget |
Agency |
| REHABILITATION of ROADS, BARANGAY UGONG NORTE, QUEZON CITY |
Ongoing |
21% |
₱19,360,483 |
Quezon City 2nd DEO |
| PREVENTIVE MAINTENANCE of ROAD: ASPHALT OVERLAY - COMMONWEALTH AVE. (S05761LZ) - K0013 + (-030) - K0013 + 222, QUEZON CITY |
Completed |
100% |
₱14,545,286 |
Quezon City 2nd DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (MORTUARY), BARANGAY MASAGANA, QUEZON CITY |
Completed |
100% |
₱9,898,840 |
Quezon City 2nd DEO |
| CONSTRUCTION of ROAD INCLUDING at MASBATE STREET, BARANGAY RAMON MAGSAYSAY, QUEZON CITY |
Completed |
100% |
₱9,799,921 |
Quezon City 1st DEO |
| ROAD IMPROVEMENT of BERNARDO STREET, BARANGAY MARIBLO, QUEZON CITY |
Completed |
100% |
₱9,509,153 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY RAMON MAGSAYSAY, QUEZON CITY |
Completed |
100% |
₱9,506,000 |
Quezon City 1st DEO |
| CONSTRUCTION of ROAD INCLUDING DRAINAGE at NUEVA ECIJIA STREET, BARANGAY RAMON MAGSAYSAY, QUEZON CITY |
Completed |
100% |
₱9,505,924 |
Quezon City 1st DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY ST. PETER, QUEZON CITY |
Completed |
100% |
₱9,486,400 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY BLUE RIDGE B, QUEZON CITY |
Completed |
100% |
₱4,940,896 |
Quezon City 2nd DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY BLUE RIDGE A, QUEZON CITY |
Completed |
100% |
₱4,808,797 |
Quezon City 2nd DEO |
| REHABILITATION/ MAJOR REPAIR of MULTI-PURPOSE BUILDING - REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY ALICIA, QUEZON CITY |
Completed |
100% |
₱4,801,500 |
Quezon City 1st DEO |
| REHABILITATION / RENOVATION of COSETENG BUILDING, BRGY. BAGUMBUHAY, DISTRICT 3, QUEZON CITY |
Completed |
100% |
₱4,801,143 |
Quezon City 2nd DEO |