| PREVENTIVE MAINTENANCE - SECONDARY ROADS - CONGRESSIONAL AVE EXT - K0016 + 294 - K0015 + 152, QUEZON CITY |
Ongoing |
87% |
₱56,747,057 |
Quezon City 1st DEO |
| REHABILITATION of PHILIPPINE INFORMATION AGENCY BUILDING, VISAYAS AVE., DILIMAN, QUEZON CITY |
Ongoing |
78% |
₱48,754,901 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURE at BARANGAY BATASAN HILLS, QUEZON CITY |
Completed |
100% |
₱48,498,874 |
Quezon City 1st DEO |
| CONCRETING of ROAD with DRAINAGE IMPROVEMENT at BANLAT ROAD, BRGY. TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱48,249,850 |
Quezon City 1st DEO |
| CONSTRUCTION of CONCRETE ROAD with DRAINAGE at TIERRA BELLA, BARANGAY CULIAT, QUEZON CITY |
Ongoing |
16% |
₱38,806,935 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD MITIGATION STRUCTURES and DRAINAGE SYSTEMS at BRGY. TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱38,768,478 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURES, BARANGAY SAUYO, QUEZON CITY |
Completed |
100% |
₱38,412,000 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at MAPAYAPA, BARANGAY PASONG TAMO, QUEZON CITY |
Ongoing |
15% |
₱29,105,656 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION of DARIO CREEK, BRGY. TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱28,809,000 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURES, BARANGAY CULIAT, QUEZON CITY |
Completed |
100% |
₱28,700,927 |
Quezon City 1st DEO |
| CONSTRUCTION of FLOOD CONTROL STRUCTURE at BARANGAY TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱28,518,000 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of MULTI-PURPOSE BUILDING, BARANGAY COMMONWEALTH, QUEZON CITY |
Completed |
100% |
₱28,212,004 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY PAYATAS, QUEZON CITY |
Completed |
100% |
₱23,265,002 |
Quezon City 1st DEO |
| CONSTRUCTION of DRAINAGE SYSTEMS at JEM 9, BRGY. TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱19,598,546 |
Quezon City 1st DEO |
| CONSTRUCTION of CONCRETE ROAD with DRAINAGE at BARANGAY TANDANG SORA, QUEZON CITY |
Ongoing |
67% |
₱19,436,847 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at VILLA ARCA, BARANGAY BAESA, QUEZON CITY |
Completed |
100% |
₱19,403,851 |
Quezon City 1st DEO |
| DRAINAGE IMPROVEMENT and CONCRETING of ROAD at TORRES, BARANGAY TANDANG SORA, QUEZON CITY |
Ongoing |
54% |
₱19,202,835 |
Quezon City 1st DEO |
| CONSTRUCTION of REVETMENT along DARIO CREEK STA. 0+020 - STA. 0+351.894(LEFT & RIGHT BANK), QUEZON CITY |
Completed |
100% |
₱19,013,963 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY BAGONG SILANGAN, QUEZON CITY |
Completed |
100% |
₱19,008,002 |
Quezon City 1st DEO |
| CONSTRUCTION/ REHABILITATION of CLEMENTE STREET, LUPANG PANGAKO, BRGY. PAYATAS, QUEZON CITY |
Completed |
100% |
₱18,909,000 |
Quezon City 1st DEO |
| REHABILITATION of ROADS at BARANGAY TANDANG SORA, QUEZON CITY |
Completed |
100% |
₱18,909,000 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at DON ENRIQUE, BRGY. HOLY SPIRIT, QUEZON CITY |
Completed |
100% |
₱18,812,000 |
Quezon City 1st DEO |
| REHABILITATION of MULTI-PURPOSE BUILDING, DON ENRIQUE HEIGHTS, BARANGAY HOLY SPIRIT, QUEZON CITY |
Ongoing |
53% |
₱14,800,201 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI-PURPOSE BUILDING at BARANGAY BALOMBATO, QUEZON CITY |
Completed |
100% |
₱14,258,960 |
Quezon City 1st DEO |
| CONSTRUCTION of MULTI - PURPOSE BUILDING, BRGY. BAGONG SILANGAN, QUEZON CITY |
Completed |
100% |
₱13,216,398 |
Quezon City 1st DEO |