← Top Contractors

By Administration

Projects
12 7 completed, 5 ongoing, 0 upcoming
Total budget
₱6,154,545,000
Citizen rating
Not yet rated
Finished on time
4 of 7 (57%) Only projects with both a target and an actual completion date can be counted.
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
C-5 Northern Link Road Proj. Segment 9.0 from NLEX to MacArthur Highway Valenzuela City RIGHT-OF-WAY Ongoing 85% ₱1,928,826,000 Metro Manila 3rd District Engineering Office
C-5 Northern Link Road Proj. Segment 8.1 from Mindanao Avenue to NLEX PAVED (CONCRETE) TO PAVED (CONCRETE) Ongoing 92% ₱1,538,050,000 Metro Manila 3rd District Engineering Office
Partial payment for the acquisition of Right-of-Way (ROW) for the properties affected by the development of NAIA Expressway Project RIGHT-OF-WAY Ongoing 88% ₱1,009,000,000 Metro Manila 1st District Engineering Office
C-5 Northern Link Road Proj. Segment 9.0 from NLEX to MacArthur Highway Valenzuela City RIGHT-OF-WAY Ongoing 86% ₱944,458,000 Metro Manila 3rd District Engineering Office
Construction/Improvement of Mindanao Avenue Extension Segment 2C (Phases I & II) Caloocan and Valenzuela Cities including Right-of-Way Acquisition Ongoing 94% ₱573,793,000 Metro Manila 3rd District Engineering Office
Pasig-Marikina River Channel Improvement Project OTHERS Completed 100% ₱60,653,000 Metro Manila 1st District Engineering Office
Supply and Installation of Surgical Lights @ Operating Room Complex PGH OTHERS Completed 100% ₱32,000,000 South Manila District Engineering Office
Metro Manila Flood Control Project West of Mangahan Floodway OTHERS Completed 100% ₱23,748,000 Metro Manila 1st District Engineering Office
Supply and Installation of Air conditioning (Variable refrigerant flow) system @ Operating Room Complex PGH OTHERS Completed 100% ₱18,000,000 South Manila District Engineering Office
ROW of the Construction of Polder Dike RIGHT-OF-WAY Completed 100% ₱12,099,000 Malabon-Navotas District Engineering Office
ROW of the construction of Longos Creek Drainage Channel Improvement RIGHT-OF-WAY Completed 100% ₱9,374,000 Malabon-Navotas District Engineering Office
ROW of the Construction of REGULATION PONDS (along Gov. Pascual Brgy. Catmon Malabon City) RIGHT-OF-WAY Completed 100% ₱4,544,000 Malabon-Navotas District Engineering Office