← Top Contractors

ANN-GIE BUILDERS

Projects
26 26 completed, 0 ongoing, 0 upcoming
Total budget
₱172,879,975
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, QUEZON CITY Completed 100% ₱28,340,951 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDINGS, BARANGAY BLUE RIDGE B, QUEZON CITY Completed 100% ₱18,990,681 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, CAMP AGUINALDO, QUEZON CITY Completed 100% ₱18,972,112 Quezon City 2nd DEO
CONSTRUCTION / REHABILITATION of MULTI-PURPOSE BUILDINGS with SITE DEVELOPMENT / PAVEMENT REHABILITATION, BARANGAY UGONG NORTE, QUEZON CITY Completed 100% ₱14,847,648 Quezon City 2nd DEO
IMPROVEMENT of MULTI-PURPOSE BUILDING, BARANGAY AMIHAN, QUEZON CITY Completed 100% ₱8,326,889 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, PROJECT 2 MARKET, QUEZON CITY Completed 100% ₱6,859,329 Quezon City 2nd DEO
CONSTRUCTION of BARANGAY MULTI-PURPOSE BUILDING (PHASE 1), BARANGAY BAGUMBAYAN, QUEZON CITY Completed 100% ₱6,597,318 Quezon City 2nd DEO
REHABILITATION of MULTI-PURPOSE BUILDING at BARANGAY LOYOLA HEIGHTS, QUEZON CITY Completed 100% ₱5,854,387 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, BRGY. WEST KAMIAS, QUEZON CITY Completed 100% ₱5,691,976 Quezon City 2nd DEO
CONSTRUCTION (COMPLETION) of MULTI-PURPOSE BUILDING at BARANGAY BLUE RIDGE B, QUEZON CITY Completed 100% ₱4,948,199 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, BARANGAY BLUE RIDGE A, QUEZON CITY Completed 100% ₱4,947,108 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT, E. RODRIGUEZ ELEMENTARY SCHOOL, QUEZON CITY Completed 100% ₱4,888,800 Quezon City 2nd DEO
CONSTRUCTION of DRAINAGE SYSTEM at BARANGAY PANSOL, QUEZON CITY Completed 100% ₱4,742,519 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY LOYOLA HEIGHTS, QUEZON CITY Completed 100% ₱4,741,731 Quezon City 2nd DEO
CONSTRUCTION, IMPROVEMENT and REHABILITATION of VARIOUS MULTI-PURPOSE BUILDING, BARANGAY OLD BALARA, QUEZON CITY Completed 100% ₱4,311,739 Quezon City 2nd DEO
CONSTRUCTION, IMPROVEMENT and REHABILITATION of MULTI-PURPOSE BUILDINGS with SITE DEVELOPMENT, BARANGAY WHITE PLAINS, QUEZON CITY Completed 100% ₱3,832,661 Quezon City 2nd DEO
CONSTRUCTION of BARANGAY MULTI-PURPOSE BUILDING and SITE DEVELOPMENT/ PAVEMENT IMPROVEMENT, BARANGAY SAINT IGNATIUS, QUEZON CITY Completed 100% ₱3,325,552 Quezon City 2nd DEO
CONSTRUCTION of BARANGAY MULTI-PURPOSE BUILDING, BARANGAY WHITE PLAINS, QUEZON CITY Completed 100% ₱3,298,625 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, QUEZON CITY Completed 100% ₱3,274,296 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY DUYAN-DUYAN, QUEZON CITY Completed 100% ₱3,273,390 Quezon City 2nd DEO
IMPROVEMENT of ROADS, BARANGAY WEST KAMIAS, QUEZON CITY Completed 100% ₱2,851,239 Quezon City 2nd DEO
CONSTRUCTION / REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY DIOQUINO ZOBEL, QUEZON CITY Completed 100% ₱2,357,466 Quezon City 2nd DEO
CONSTRUCTION, IMPROVEMENT and REHABILITATION of MULTI-PURPOSE BUILDING at QUIRINO HIGH SCHOOL, QUEZON CITY Completed 100% ₱1,920,391 Quezon City 2nd DEO
IMPROVEMENT and REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY EAST KAMIAS, QUEZON CITY Completed 100% ₱1,915,820 Quezon City 2nd DEO
REHABILITATION of VARIOUS MULTI-PURPOSE BUILDINGS, BARANGAY QUIRINO 2-C, QUEZON CITY Completed 100% ₱1,884,638 Quezon City 2nd DEO

Show all 26 projects