Projects
12 10 completed, 2 ongoing, 0 upcoming
Total budget
₱522,657,543
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
REHABILITATION of ACADEMIC MULTI-PURPOSE BUILDING at UNIVERSITY of the PHILIPPINES, DILIMAN, QUEZON CITY Completed 100% ₱55,644,482 Quezon City 2nd DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURE along ILANG-ILANG CREEK LEADING to TULLAHAN RIVER at BRGY. COMMONWEALTH, QUEZON CITY Completed 100% ₱53,469,803 Flood Control Management Cluster
CONSTRUCTION of FLOOD CONTROL STRUCTURE along MARIBLO CREEK (PHASE 2), BARANGAY STA. CRUZ, QUEZON CITY Ongoing 59% ₱48,509,572 Quezon City 1st DEO
CONSTRUCTION of FLOOD CONTROL STRUCTURE at DARIO CREEK, BARANGAY BAHAY TORO, QUEZON CITY Completed 100% ₱48,508,406 Quezon City 1st DEO
REHABILITATION of SAN JUAN RIVER, PHASE 1, QUEZON CITY Ongoing 0% ₱48,006,858 Quezon City 2nd DEO
CONSTRUCTION of MULTI-LEVEL PARKING at CAMP KARINGAL, QUEZON CITY Completed 100% ₱47,530,341 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY BAHAY TORO, QUEZON CITY Completed 100% ₱47,530,000 Quezon City 1st DEO
REHABILITATION of ROAD at BRGY. COMMONWEALTH, QUEZON CITY Completed 100% ₱38,412,000 Quezon City 1st DEO
IMPROVEMENT of ROADS, at BARANGAY KRUS NA LIGAS, QUEZON CITY Completed 100% ₱37,521,172 Quezon City 2nd DEO
REHABILITATION / RECONSTRUCTION / UPGRADING of DAMAGED PAVED ROADS - TERTIARY ROADS - INTERNAL RD - CHAINAGE 0 - CHAINAGE 979, QUEZON CITY Completed 100% ₱36,052,511 Quezon City 2nd DEO
MAJOR REPAIR of VARIOUS CENTER / RESIDENTIAL CARE FACILITIES of DSWD, QUEZON CITY: A) PAL BUILDING - REHABILITATION SHELTERED WORKSHOP; B) MAIN BUILDING - NATIONAL VOCATIONAL REHABILITATION CENTER; C) TWO STOREY COTTAGE with BASEMENT - SILUNGAN..... Completed 100% ₱32,002,008 Quezon City 2nd DEO
CONSTRUCTION of 4 STOREY-8 CLASSROOM BUILDING, QUIRINO HIGH SCHOOL, QUEZON CITY 3RD LD Completed 100% ₱29,470,391 Quezon City 2nd DEO