← Top Contractors

4 DOUBLERS TRADING & CONTRACTOR INC. (FORMERLY: 4 DOUBLERS TRADING AND CONTRACTOR)

Projects
36 30 completed, 6 ongoing, 0 upcoming
Total budget
₱356,121,433
Citizen rating
Not yet rated
Finished on time
No data
Public reports
0

How to read these numbers

Where the data comes from
Projects, budgets and dates come from the public records of the Department of Public Works and Highways (DPWH), as published. They may be incomplete or out of date.
What a rating means
A rating is the opinion of the residents who left it. It is not an audit.
What a report means
A report is a problem a resident filed and confirmed by email. It is not a finding that the contractor is at fault. “Looked at” means LGU staff have acknowledged or acted on it.

If something here is wrong, tell us through the contact form.

Reply as this contractor

Draft for review: this explanation has not yet been checked by an expert.

Projects

Project Status Progress Budget Agency
CONSTRUCTION (COMPLETION) of ROAD and DRAINAGE along GOZUM ST., BARANGAY NAGKAISANG NAYON, QUEZON CITY Completed 100% ₱29,399,190 Quezon City 1st DEO
REHABILITATION of FLOOD CONTROL STRUCTURE at BARANGAY BAGBAG, QUEZON CITY Ongoing 72% ₱29,106,000 Quezon City 1st DEO
REHABILITATION of MULTI-PURPOSE BUILDING, BARANGAY QUIRINO 2A, QUEZON CITY Completed 100% ₱19,798,985 Quezon City 2nd DEO
PREVENTIVE MAINTENANCE of ROAD: ASPHALT OVERLAY - QUIRINO HI-WAY - K0018 + 000 - K0019 + 000, QUEZON CITY Completed 100% ₱18,194,716 Quezon City 1st DEO
IMPROVEMENT of ROADS, at BARANGAY PINYAHAN, QUEZON CITY Completed 100% ₱14,554,725 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING in BARANGAY PASONG PUTIK, NOVALICHES, QUEZON CITY Ongoing 18% ₱14,551,358 Quezon City 1st DEO
RETROFITTING/STRENGTHENING of PERMANENT BRIDGES - PASONG TAMO BR. 2 (SB) (B02355LZ) along VISAYAS AVE, QUEZON CITY Completed 100% ₱14,547,029 Quezon City 1st DEO
RETROFITTING / STRENGTHENING of PERMANENT BRIDGE - PASONG TAMO BRIDGE 2 (NB) (B02357LZ), QUEZON CITY Completed 100% ₱14,544,034 Quezon City 1st DEO
PREVENTIVE MAINTENANCE of ROAD: ASPHALT OVERLAY - QUIRINO HI-WAY - K0022 + 000 - K0023 + 000, QUEZON CITY Completed 100% ₱13,441,184 Quezon City 1st DEO
REHABILITATION of ROAD at BARANGAY CENTRAL, QUEZON CITY Completed 100% ₱11,756,449 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, BARANGAY BLUE RIDGE B, QUEZON CITY Completed 100% ₱11,755,100 Quezon City 2nd DEO
STRUCTURAL IMPROVEMENT of PUBLIC BUILDINGS and CONSTRUCTION of EVACUATION CENTER, NATIONAL CAPITAL REGION RAMON MAGSAYSAY HIGH SCHOOL, H.E. BUILDING, QUEZON CITY Completed 100% ₱11,024,512 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, PHASE II, OLD BALARA ELEMENTARY SCHOOL, QUEZON CITY Completed 100% ₱9,896,829 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING with SITE DEVELOPMENT at BARANGAY BAGUMBAYAN, QUEZON CITY Completed 100% ₱9,883,335 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING for BRGY. NOVA PROPER, NOVALICHES, QUEZON CITY Completed 100% ₱9,602,998 Quezon City 1st DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY PANSOL, QUEZON CITY Completed 100% ₱9,486,317 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING in BARANGAY QUIRINO 2B, QUEZON CITY Ongoing 16% ₱8,624,382 Quezon City 2nd DEO
IMPROVEMENT of ROADS, at BARANGAY SACRED HEART, QUEZON CITY Completed 100% ₱7,796,674 Quezon City 2nd DEO
CONSTRUCTION of MULTI-PURPOSE BUILDING, BARANGAY KAUNLARAN, QUEZON CITY Completed 100% ₱7,749,758 Quezon City 2nd DEO
REHABILITATION of MULTI-PURPOSE BUILDING in BARANGAY MASAGANA, QUEZON CITY Completed 100% ₱7,664,374 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, BARANGAY OLD BALARA, QUEZON CITY Completed 100% ₱6,858,042 Quezon City 2nd DEO
PREVENTIVE MAINTENANCE of ROAD: CONCRETE REBLOCKING - CAMP AGUINALDO RD NETWORK (S05546LZ) - CHAINAGE 0 - CHAINAGE 804, QUEZON CITY Completed 100% ₱6,825,249 Quezon City 2nd DEO
REHABILITATION of ROADS, BRGY. WEST KAMIAS, QUEZON CITY Ongoing 99% ₱6,651,877 Quezon City 2nd DEO
REHABILITATION of DRAINAGE SYSTEM, BARANGAY SAINT IGNATIUS, QUEZON CITY Completed 100% ₱5,644,714 Quezon City 2nd DEO
PREVENTIVE MAINTENANCE of ROAD: CONCRETE REBLOCKING - CAMP AGUINALDO RD NETWORK - (S05559LZ) CHAINAGE 0 - CHAINAGE 640, QUEZON CITY Completed 100% ₱5,432,163 Quezon City 2nd DEO

Show all 36 projects